Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Naples Island Pump Stations Rehabilitation - Phase I
Contractor: MMC, Inc.
5901 Fresca Drive
La Palma, CA 90623
Project ID: FCC0001392
Federal Number(s): None
Original Contract: $5,854,700.00
Awarded: 6/21/2023
Period Ending: 6/15/2024
Board Accepted: 7/30/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 1.00 0.001.00$2,500.00$2,500.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)4.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.25 0.000.25$10,000.00$2,500.00
5IMPLEMENTATION OF BMPS1.00LS 0.25 0.000.25$60,000.00$15,000.00
6CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $25,000)25,000.00AL 36,447.19 0.0036,447.19$1.00$36,447.19
7PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
8IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.25 0.000.25$25,000.00$6,250.00
10PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
11IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.25 0.000.25$25,000.00$6,250.00
12OFFICE FACILITIES5.00MTH 1.00 0.001.00$20,000.00$20,000.00
13MOBILIZATION1.00LS 0.95 0.000.95$300,000.00$285,000.00
15DEMOLITION1.00LS 0.60 0.000.60$390,000.00$234,000.00
16TRASH RACK1.00LS 0.10 0.000.10$400,000.00$40,000.00
21ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION1.00LS 0.23 0.000.23$600,000.00$138,000.00
22ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION1.00LS 0.39 0.000.39$600,000.00$234,000.00
23ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION1.00LS 0.23 0.000.23$600,000.00$138,000.00
24STRUCTURE CONCRETE10.00CY 5.58 0.005.58$6,000.00$33,480.00
25DRILL AND BOND DOWEL (EPOXY CARTRIDGE)261.00LF 60.00 0.0060.00$200.00$12,000.00
26TRAFFIC HATCH DOOR5.00EA 4.00 0.004.00$60,000.00$240,000.00
28REMOVE EXISTING CONCRETE1.00LS 0.40 0.000.40$76,000.00$30,400.00
29TRAFFIC CONTROL1.00LS 0.30 0.000.30$200,000.00$60,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,540,327.19 $0.00 $1,540,327.19
Retained $77,016.36 $0.00 $77,016.36
Deducted $0.00 $0.00 $0.00
Due $1,463,310.83 $0.00 $1,463,310.83