| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.25
| 0.00 | 0.25 | $10,000.00 | $2,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.25
| 0.00 | 0.25 | $60,000.00 | $15,000.00 |
| 6 | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $25,000) | 25,000.00 | AL |
36,447.19
| 0.00 | 36,447.19 | $1.00 | $36,447.19 |
| 7 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
| 10 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
| 12 | OFFICE FACILITIES | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $20,000.00 | $20,000.00 |
| 13 | MOBILIZATION | 1.00 | LS |
0.95
| 0.00 | 0.95 | $300,000.00 | $285,000.00 |
| 15 | DEMOLITION | 1.00 | LS |
0.60
| 0.00 | 0.60 | $390,000.00 | $234,000.00 |
| 16 | TRASH RACK | 1.00 | LS |
0.10
| 0.00 | 0.10 | $400,000.00 | $40,000.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
0.23
| 0.00 | 0.23 | $600,000.00 | $138,000.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
0.39
| 0.00 | 0.39 | $600,000.00 | $234,000.00 |
| 23 | ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION | 1.00 | LS |
0.23
| 0.00 | 0.23 | $600,000.00 | $138,000.00 |
| 24 | STRUCTURE CONCRETE | 10.00 | CY |
5.58
| 0.00 | 5.58 | $6,000.00 | $33,480.00 |
| 25 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 261.00 | LF |
60.00
| 0.00 | 60.00 | $200.00 | $12,000.00 |
| 26 | TRAFFIC HATCH DOOR | 5.00 | EA |
4.00
| 0.00 | 4.00 | $60,000.00 | $240,000.00 |
| 28 | REMOVE EXISTING CONCRETE | 1.00 | LS |
0.40
| 0.00 | 0.40 | $76,000.00 | $30,400.00 |
| 29 | TRAFFIC CONTROL | 1.00 | LS |
0.30
| 0.00 | 0.30 | $200,000.00 | $60,000.00 |
|