| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 11.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
0.27
| 0.00 | 0.27 | $1,000.00 | $270.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.27
| 0.18 | 0.09 | $10,000.00 | $900.00 |
| 6 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.27
| 0.18 | 0.09 | $5,000.00 | $450.00 |
| 76 | TYPE 332 CABINET | 10.00 | EA |
10.00
| 0.00 | 10.00 | $19,865.00 | $198,650.00 |
| 105 | PEDESTRIAN PUSH BUTTON | 65.00 | EA |
25.00
| 0.00 | 25.00 | $3,658.00 | $91,450.00 |
| 111 | 3-12" LED VEHICLE HEAD (COMPLETE) | 139.00 | EA |
139.00
| 0.00 | 139.00 | $1,488.00 | $206,832.00 |
| 132 | TRAFFIC CONTROL | 1.00 | LS |
0.27
| 0.18 | 0.09 | $88,884.00 | $7,999.56 |