Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 11.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.10
| 0.00 | 0.10 | $20,000.00 | $2,000.00 |
6 | PREPARATION OF THE SWPPP (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.10
| 0.00 | 0.10 | $40,000.00 | $4,000.00 |
8 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.00 | 1.00 | $18,000.00 | $18,000.00 |
9 | OFFICE FACILITIES | 12.00 | MTH |
1.00
| 0.00 | 1.00 | $7,500.00 | $7,500.00 |
10 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $554,000.00 | $277,000.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 297.00 | CY |
131.42
| 0.00 | 131.42 | $375.00 | $49,282.50 |
13 | UNCLASSIFIED EXCAVATION | 352.00 | CY |
73.23
| 0.00 | 73.23 | $250.00 | $18,307.50 |
15 | CRUSHED MISCELLANEOUS BASE | 177.00 | CY |
64.45
| 0.00 | 64.45 | $280.00 | $18,046.00 |
17 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 6.00 | CY |
6.00
| 0.00 | 6.00 | $400.00 | $2,400.00 |
20 | AC PAVEMENT | 8,700.00 | TON |
36.31
| 0.00 | 36.31 | $110.00 | $3,994.10 |
35 | REMOVE AND DISPOSE OF EXISTING CATCH BASIN AND CONNECTOR PIPE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
39 | CURB DRAIN PER STD PLAN 150, N=1, CASE 2 INLET | 4.00 | EA |
2.00
| 0.00 | 2.00 | $2,500.00 | $5,000.00 |
44 | PCC CURB & GUTTER, TYPE A2-8 | 590.00 | LF |
62.00
| 0.00 | 62.00 | $95.00 | $5,890.00 |
46 | PCC CURB & GUTTER, TYPE A2-VAR | 751.00 | LF |
226.00
| 0.00 | 226.00 | $115.00 | $25,990.00 |
47 | PCC WALK & DRIVEWAYS, 4" THICK | 7,714.00 | SF |
2,187.00
| 0.00 | 2,187.00 | $11.00 | $24,057.00 |
48 | PCC CURB RAMPS | 70.00 | CY |
4.50
| 0.00 | 4.50 | $1,100.00 | $4,950.00 |
53 | SUPPORT FOR 8" WATERLINE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $12,000.00 | $12,000.00 |
54 | SUPPORT FOR 10" GAS LINE | 1.00 | EA |
1.00
| 0.00 | 1.00 | $16,000.00 | $16,000.00 |
55 | 18" RCP, 1500 D | 52.00 | LF |
41.00
| 0.00 | 41.00 | $625.00 | $25,625.00 |
64 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 4.00 | EA |
4.00
| 0.00 | 4.00 | $1,320.00 | $5,280.00 |
139 | TRAFFIC CONTROL | 1.00 | LS |
0.085
| 0.00 | 0.085 | $360,000.00 | $30,600.00 |
S-4 | REVISED STORM DRAIN WORK | | LS |
0.85
| 0.00 | 0.85 | $45,670.00 | $38,819.50 |
|