Los Angeles County Public Works
Project Management Division III
Progress Payment 2
Project Name: Project No 450 - Alamitos Bay Pump Station - Discharge Line Replacement
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: FCC0001218
Federal Number(s): None
Original Contract: $5,397,430.00
Awarded: 6/27/2023
Period Ending: 7/10/2024
Board Accepted: 5/13/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)4.00MTH 2.00 1.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.50 0.250.25$15,000.00$3,750.00
5IMPLEMENTATION OF BMPS1.00LS 0.50 0.250.25$45,000.00$11,250.00
8MAINTENANCE OF TEMPORARY SOUND BARRIER60.00LF 30.00 15.0015.00$30.00$450.00
14IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN1.00LS 0.50 0.250.25$15,000.00$3,750.00
16TRANSPORTATION AND DISPOSAL OF TREATED WOOD WASTE1.00LS 1.00 0.001.00$55,780.00$55,780.00
18IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.50 0.000.50$6,000.00$3,000.00
19REMOVAL AND DISPOSAL OF LBP/LCP1.00LS 1.00 0.001.00$11,000.00$11,000.00
21IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN1.00LS 0.50 0.000.50$5,500.00$2,750.00
22REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIAL1.00LS 1.00 0.001.00$18,030.00$18,030.00
24OFFICE FACILITIES4.00MTH 2.00 1.001.00$3,500.00$3,500.00
25MOBILIZATION1.00LS 0.95 0.750.20$323,600.00$64,720.00
28UNCLASSIFIED EXCAVATION169.00CY 84.00 0.0084.00$200.00$16,800.00
30STRUCTURE EXCAVATION54.00CY 27.00 0.0027.00$265.00$7,155.00
32CONSTRUCT AND REMOVE COFFERDAM1.00EA 0.60 0.400.20$1,639,519.00$327,903.80
47TEMPORARY BOATYARD1.00LS 0.50 0.420.08$67,580.00$5,406.40
51HDPE PIPES1.00LS 0.28 0.000.28$248,271.00$69,515.88
60STEEL PIPES REMOVAL1.00LS 1.00 0.340.66$39,850.00$26,301.00
64TRAFFIC CONTROL1.00LS 0.25 0.000.25$196,500.00$49,125.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 32.00 19.0013.00$100.00 $1,300.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,801,574.07 $1,120,886.99 $680,687.08
Retained* $90,078.70 $56,044.35 $34,034.35
Deducted $3,200.00 $1,900.00 $1,300.00
Due $1,708,295.37 $1,062,942.64 $645,352.73



*This project has an escrow account.

Contact Office Engineer