| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 4 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 12 | CITIES PERMIT AND INSPECTION FEES (ALLOWANCE OF $16,000) | 16,000.00 | AL |
490.00
| 0.00 | 490.00 | $1.00 | $490.00 |
| 13 | OFFICE FACILITIES | 4.00 | MTH |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
| 16 | TRAFFIC CONTROL | 1.00 | LS |
0.25
| 0.00 | 0.25 | $228,771.00 | $57,192.75 |
| 17 | FLASHING ARROW SIGN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $5,000.00 | $1,250.00 |
| 18 | CHANGEABLE MESSAGE SIGN | 1.00 | LS |
0.25
| 0.00 | 0.25 | $50,000.00 | $12,500.00 |
| 19 | TEMPORARY RAILING (TYPE K) | 430.00 | LF |
400.00
| 0.00 | 400.00 | $65.00 | $26,000.00 |
| 20 | BRIDGE REMOVAL (PORTIONS) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $175,000.00 | $175,000.00 |
| 39 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DECK) | 358.00 | SF |
107.50
| 0.00 | 107.50 | $185.00 | $19,887.50 |
| 40 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (SIDEWALK) | 33.00 | SF |
13.00
| 0.00 | 13.00 | $685.00 | $8,905.00 |
| 41 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (BARRIER) | 73.00 | SF |
20.00
| 0.00 | 20.00 | $330.00 | $6,600.00 |
| 42 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (SOFFIT) | 7.00 | SF |
7.00
| 0.00 | 7.00 | $1,650.00 | $11,550.00 |
| 43 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (ABUTMENT) | 66.00 | SF |
63.00
| 0.00 | 63.00 | $310.00 | $19,530.00 |
| 44 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (PIER) | 33.00 | SF |
33.00
| 0.00 | 33.00 | $1,080.00 | $35,640.00 |
| 45 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DIAPHRAGM) | 22.00 | SF |
20.00
| 0.00 | 20.00 | $1,350.00 | $27,000.00 |
| 46 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (GIRDER) | 467.00 | SF |
395.00
| 0.00 | 395.00 | $235.00 | $92,825.00 |
| 47 | RAPID SETTING CONCRETE PATCH (DECK) | 358.00 | SF |
107.50
| 0.00 | 107.50 | $235.00 | $25,262.50 |
| 48 | REPAIR SPALLED CONCRETE (SIDEWALK) | 33.00 | SF |
13.00
| 0.00 | 13.00 | $715.00 | $9,295.00 |
| 49 | REPAIR SPALLED CONCRETE (BARRIER) | 73.00 | SF |
20.00
| 0.00 | 20.00 | $360.00 | $7,200.00 |
| 50 | REPAIR SPALLED CONCRETE (SOFFIT) | 7.00 | SF |
7.00
| 0.00 | 7.00 | $1,325.00 | $9,275.00 |
| 51 | REPAIR SPALLED CONCRETE (ABUTMENT) | 66.00 | SF |
63.00
| 0.00 | 63.00 | $360.00 | $22,680.00 |
| 52 | REPAIR SPALLED CONCRETE (PIER) | 33.00 | SF |
33.00
| 0.00 | 33.00 | $1,115.00 | $36,795.00 |
| 53 | REPAIR SPALLED CONCRETE (DIAPHRAGM) | 22.00 | SF |
20.00
| 0.00 | 20.00 | $1,365.00 | $27,300.00 |
| 54 | REPAIR SPALLED CONCRETE (GIRDER) | 467.00 | SF |
395.00
| 0.00 | 395.00 | $280.00 | $110,600.00 |
| S-2 | INSTALLATION OF SLED TYPE 2 ATTENUATOR AND TEMPORARY FENCING ON ARTESIA BLVD | | LS |
1.00
| 0.00 | 1.00 | $17,821.25 | $17,821.25 |