| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.45
| 0.25 | 0.20 | $10,000.00 | $2,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.45
| 0.25 | 0.20 | $60,000.00 | $12,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.45
| 0.25 | 0.20 | $25,000.00 | $5,000.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.45
| 0.25 | 0.20 | $25,000.00 | $5,000.00 |
| 12 | OFFICE FACILITIES | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $20,000.00 | $20,000.00 |
| 15 | DEMOLITION | 1.00 | LS |
0.80
| 0.60 | 0.20 | $390,000.00 | $78,000.00 |
| 16 | TRASH RACK | 1.00 | LS |
0.30
| 0.10 | 0.20 | $400,000.00 | $80,000.00 |
| 17 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $600,000.00 | $120,000.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
0.44
| 0.23 | 0.21 | $600,000.00 | $126,000.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
0.44
| 0.39 | 0.05 | $600,000.00 | $30,000.00 |
| 24 | STRUCTURE CONCRETE | 10.00 | CY |
7.66
| 5.58 | 2.08 | $6,000.00 | $12,480.00 |
| 25 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 261.00 | LF |
177.50
| 60.00 | 117.50 | $200.00 | $23,500.00 |
| 26 | TRAFFIC HATCH DOOR | 5.00 | EA |
5.00
| 4.00 | 1.00 | $60,000.00 | $60,000.00 |
| 28 | REMOVE EXISTING CONCRETE | 1.00 | LS |
0.90
| 0.40 | 0.50 | $76,000.00 | $38,000.00 |
| 29 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.30 | 0.20 | $200,000.00 | $40,000.00 |
| S-1 | EXTENSION OF TIME, PART 1 NTP | | WD |
26.00
| 0.00 | 26.00 | $0.00 | $0.00 |