| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.90
| 0.80 | 0.10 | $23,000.00 | $2,300.00 |
| 8 | CONCRETE REMOVAL (NON-REINFORCED) | 282.00 | CY |
293.00
| 282.00 | 11.00 | $450.00 | $4,950.00 |
| 10 | UNCLASSIFIED EXCAVATION | 532.00 | CY |
593.00
| 532.00 | 61.00 | $350.00 | $21,350.00 |
| 11 | CRUSHED MISCELLANEOUS BASE | 482.00 | CY |
523.00
| 482.00 | 41.00 | $219.00 | $8,979.00 |
| 12 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 23.00 | CY |
26.00
| 23.00 | 3.00 | $200.00 | $600.00 |
| 17 | AC PAVEMENT(PATCH BACK) | 38.00 | TON |
45.00
| 38.00 | 7.00 | $295.00 | $2,065.00 |
| 19 | DOUBLE ADJUST MANHOLE | 52.00 | EA |
26.00
| 0.00 | 26.00 | $1,000.00 | $26,000.00 |
| 26 | PCC CURB & GUTTER, TYPE A2-6 | 40.00 | LF |
73.50
| 40.00 | 33.50 | $96.00 | $3,216.00 |
| 28 | PCC CURB & GUTTER, TYPE A2-VAR | 586.00 | LF |
616.00
| 586.00 | 30.00 | $96.00 | $2,880.00 |
| 29 | PCC WALK, 4" THICK | 2,286.00 | SF |
3,456.00
| 2,286.00 | 1,170.00 | $15.00 | $17,550.00 |
| 31 | PCC DRIVEWAYS, 6" THICK | 36.00 | SF |
336.00
| 36.00 | 300.00 | $23.00 | $6,900.00 |
| 39 | 2" CONDUIT (SCH 80 PVC) | 20.00 | LF |
20.00
| 0.00 | 20.00 | $125.00 | $2,500.00 |
| 40 | 3" CONDUIT (SCH 80 PVC) | 95.00 | LF |
95.00
| 0.00 | 95.00 | $110.00 | $10,450.00 |
| 73 | 3-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 448.00 | LF |
448.00
| 0.00 | 448.00 | $4.00 | $1,792.00 |
| 74 | 5-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 453.00 | LF |
453.00
| 0.00 | 453.00 | $4.00 | $1,812.00 |
| 75 | 12-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT) | 453.00 | LF |
453.00
| 0.00 | 453.00 | $8.00 | $3,624.00 |
| 76 | #10 WIRE | 453.00 | LF |
453.00
| 0.00 | 453.00 | $2.00 | $906.00 |
| 96 | TRAFFIC CONTROL | 1.00 | LS |
0.95
| 0.90 | 0.05 | $562,000.00 | $28,100.00 |
| S-3 | ADDITIONAL TRAFFIC CONTROL | | T&M |
928.97
| 0.00 | 928.97 | $1.00 | $928.97 |
| S-4 | LOSS OF PRODUCTION | | T&M |
3,598.86
| 0.00 | 3,598.86 | $1.00 | $3,598.86 |