Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Ladera Heights - Centinela Avenue et al
Contractor: Access Pacific, Inc.
2835 Sierra Grande Street
Pasadena, CA 91107
Project ID: RDC0012971
Federal Number(s): None
Original Contract: $2,586,110.99
Awarded: 11/8/2023
Period Ending: 8/6/2024
Board Accepted: 3/11/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF THE LTWHP1.00LS 0.90 0.750.15$15,000.00$2,250.00
5IMPLEMENTATION OF BMPS1.00LS 0.90 0.750.15$25,000.00$3,750.00
7OFFICE FACILITIES4.00MTH 4.00 3.001.00$5,000.00$5,000.00
10CONCRETE REMOVAL (NON-REINFORCED)100.00CY 99.98 96.103.88$450.00$1,746.00
11UNCLASSIFIED EXCAVATION549.00CY 551.91 549.002.91$180.00$523.80
13CRUSHED MISCELLANEOUS BASE319.00CY 360.81 319.0041.81$160.00$6,689.60
14TRENCH BACKFILL SLURRY (CLASS 270-E-500)17.00CY 18.94 17.001.94$400.00$776.00
15COLD MILL AC PAVEMENT (> 1-1/2 - 3")425,462.00SF 425,462.00 0.00425,462.00$0.77$327,605.74
16COLD MILL AC PAVEMENT (> 3")1,240.00SF 1,240.00 0.001,240.00$2.87$3,558.80
18AC PAVEMENT(PATCH BACK)34.00TON 37.88 34.003.88$300.00$1,164.00
19AC PAVEMENT(LEVELING COURSE)1,973.00TON 1,973.00 0.001,973.00$150.00$295,950.00
22CLEAN AND PAINT EXISTING MANHOLE1.00LS 1.00 0.001.00$1,500.00$1,500.00
24ASPHALT RUBBER HOT MIX3,454.00TON 3,167.00 0.003,167.00$160.00$506,720.00
25ASPHALT RUBBER HOT MIX (TEST STRIP)500.00TON 500.00 0.00500.00$170.00$85,000.00
33PCC CURB & GUTTER, TYPE A2-846.00LF 124.50 46.0078.50$75.00$5,887.50
34PCC CURB & GUTTER, TYPE A2-VAR204.00LF 331.00 204.00127.00$75.00$9,525.00
61TRAFFIC CONTROL1.00LS 0.90 0.750.15$200,000.00$30,000.00
62FLASHING ARROW SIGN6.00EA 6.00 3.003.00$5,000.00$15,000.00
71FORMED STEEL TROUGH AND NARROW SLOT TRENCH GRATE WITH FRAME1.00EA 1.00 0.001.00$5,300.00$5,300.00
72STAINLESS STEEL DEBRIS MESH AND FRAME1.00EA 1.00 0.001.00$3,400.00$3,400.00
74FURNISH AND PLANT 5 GALLON SHRUBS6.00EA 6.00 0.006.00$150.00$900.00
75FURNISH AND PLANT 1 GALLON SHRUB42.00EA 42.00 0.0042.00$70.00$2,940.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,346,671.04 $1,031,484.60 $1,315,186.44
Retained $117,333.56 $51,574.23 $65,759.33
Deducted $0.00 $0.00 $0.00
Due $2,229,337.48 $979,910.37 $1,249,427.11