| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.75
| 0.50 | 0.25 | $15,000.00 | $3,750.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $45,000.00 | $11,250.00 |
| 8 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 60.00 | LF |
45.00
| 30.00 | 15.00 | $30.00 | $450.00 |
| 14 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $15,000.00 | $3,750.00 |
| 18 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $6,000.00 | $1,500.00 |
| 21 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
0.75
| 0.50 | 0.25 | $5,500.00 | $1,375.00 |
| 24 | OFFICE FACILITIES | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $3,500.00 | $3,500.00 |
| 30 | STRUCTURE EXCAVATION | 54.00 | CY |
42.93
| 27.00 | 15.93 | $265.00 | $4,221.45 |
| 35 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 88.00 | LF |
41.65
| 0.00 | 41.65 | $150.00 | $6,247.50 |
| 37 | STRUCTURAL STEEL | 13,588.00 | LB |
2,718.00
| 0.00 | 2,718.00 | $16.50 | $44,847.00 |
| 46 | NON-STRUCTURAL FINISHING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $30,360.00 | $15,180.00 |
| 47 | TEMPORARY BOATYARD | 1.00 | LS |
0.55
| 0.50 | 0.05 | $67,580.00 | $3,379.00 |
| 57 | REFURBISH EXISTING LOUVERS AND ENCLOSURES | 1.00 | LS |
0.25
| 0.00 | 0.25 | $25,000.00 | $6,250.00 |
| 59 | DISCHARGE STRUCTURE REMOVAL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $36,360.00 | $36,360.00 |
| 61 | PUMP STATION REMOVAL (PORTION) | 1.00 | LS |
0.75
| 0.00 | 0.75 | $43,000.00 | $32,250.00 |
| 64 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.25 | 0.25 | $196,500.00 | $49,125.00 |