Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.96
| 0.95 | 0.01 | $23,000.00 | $230.00 |
15 | CONCRETE REMOVAL (NON-REINFORCED) | 3,146.00 | CY |
2,550.89
| 2,527.87 | 23.02 | $200.00 | $4,604.00 |
17 | UNCLASSIFIED EXCAVATION | 4,651.00 | CY |
4,388.76
| 4,260.30 | 128.46 | $135.00 | $17,342.10 |
20 | COLD MILL AC PAVEMENT (2" - 3") | 1,422,410.00 | SF |
831,323.00
| 45,423.00 | 785,900.00 | $0.43 | $337,937.00 |
23 | AC PAVEMENT(PATCH BACK) | 1,008.00 | TON |
472.46
| 462.89 | 9.57 | $200.00 | $1,914.00 |
30 | PMAC PAVEMENT | 18,979.00 | TON |
10,005.75
| 0.00 | 10,005.75 | $112.00 | $1,120,644.00 |
44 | PCC WALK, 4" THICK | 40,585.00 | SF |
41,146.45
| 40,653.60 | 492.85 | $10.00 | $4,928.50 |
51 | METAL HAND RAILINGS PER STD PLAN 606, TYPE C | 270.00 | LF |
54.00
| 0.00 | 54.00 | $420.00 | $22,680.00 |
93 | TRAFFIC CONTROL | 1.00 | LS |
0.96
| 0.95 | 0.01 | $211,000.00 | $2,110.00 |
|