| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | PREPARATION OF THE SURFACE WATER DIVERSION PLAN (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 2 | PREPARATION OF THE FUGITIVE DUST CONTROL PLAN (STIPULATED UNIT PRICE OF $1,500/YEAR) | 2.00 | YR |
1.00
| 0.00 | 1.00 | $1,500.00 | $1,500.00 |
| 3 | PREPARATION OF THE SPILL PREVENTION AND CONTROL PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 4 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.00 | 0.50 | $365,000.00 | $182,500.00 |
| 5 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.50
| 0.00 | 0.50 | $30,000.00 | $15,000.00 |
| 6 | CITY PERMIT AND INSPECTION FEES (ALLOWANCE OF $10,000) | 10,000.00 | AL |
460.00
| 0.00 | 460.00 | $1.00 | $460.00 |
| 7 | CONSTRUCTION SCHEDULE (BASELINE) (2024) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 8 | CONSTRUCTION SCHEDULE (UPDATE) (2024) (STIPULATED UNIT PRICE OF $500/MTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 9 | IMPLEMENTATION OF BMPS (2024) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $20,000.00 | $20,000.00 |
| 10 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN (2024) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $400,000.00 | $400,000.00 |
| 11 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN (2024) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 12 | OFFICE FACILITIES (2024) | 5.00 | MTH |
2.00
| 0.00 | 2.00 | $12,000.00 | $24,000.00 |
| 13 | CLEARING AND GRUBBING (2024) | 34.00 | AC |
17.00
| 0.00 | 17.00 | $10,000.00 | $170,000.00 |
| 14 | WATER TRUCKS (2024) | 100.00 | DAYS |
27.00
| 0.00 | 27.00 | $1,100.00 | $29,700.00 |
| 15 | MOBILIZATION (2024) | 1.00 | LS |
0.75
| 0.00 | 0.75 | $605,000.00 | $453,750.00 |
| 16 | INSTALLATION OF EXCLUSIONARY FENCE (2024) | 9,100.00 | LF |
9,100.00
| 0.00 | 9,100.00 | $10.00 | $91,000.00 |
| 17 | MAINTENANCE OF EXCLUSIONARY FENCE (2024) | 9,100.00 | LF |
1,820.00
| 0.00 | 1,820.00 | $2.50 | $4,550.00 |
| 24 | PORTABLE SCALES (2024) | 100.00 | DAYS |
24.00
| 0.00 | 24.00 | $1,500.00 | $36,000.00 |
| 25 | RESERVOIR EXCAVATION (2024) | 202,500.00 | TON |
36,811.50
| 0.00 | 36,811.50 | $4.50 | $165,651.75 |
| 26 | STREET SWEEPING (2024) | 100.00 | DAYS |
7.00
| 0.00 | 7.00 | $2,800.00 | $19,600.00 |
| 27 | INSTALLATION OF TIRE WASH (2024) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $60,000.00 | $120,000.00 |
| S-1 | EXTEND NTP PART 1 DURATION | | WD |
9.00
| 0.00 | 9.00 | $0.00 | $0.00 |
| S-2 | LOCATE FIELD OFFICE WITHIN PROJECT SITE | | LS |
1.00
| 0.00 | 1.00 | $0.00 | $0.00 |
|