| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.60
| 0.45 | 0.15 | $10,000.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.45 | 0.15 | $60,000.00 | $9,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.60
| 0.45 | 0.15 | $25,000.00 | $3,750.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
0.66
| 0.00 | 0.66 | $90,000.00 | $59,400.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.60
| 0.45 | 0.15 | $25,000.00 | $3,750.00 |
| 12 | OFFICE FACILITIES | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $20,000.00 | $20,000.00 |
| 16 | TRASH RACK | 1.00 | LS |
0.60
| 0.30 | 0.30 | $400,000.00 | $120,000.00 |
| 17 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
0.50
| 0.20 | 0.30 | $600,000.00 | $180,000.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
0.46
| 0.44 | 0.02 | $600,000.00 | $12,000.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
0.45
| 0.44 | 0.01 | $600,000.00 | $6,000.00 |
| 23 | ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION | 1.00 | LS |
0.40
| 0.23 | 0.17 | $600,000.00 | $102,000.00 |
| 24 | STRUCTURE CONCRETE | 10.00 | CY |
9.88
| 7.66 | 2.22 | $6,000.00 | $13,320.00 |
| 25 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 261.00 | LF |
229.83
| 177.50 | 52.33 | $200.00 | $10,466.00 |
| 29 | TRAFFIC CONTROL | 1.00 | LS |
0.70
| 0.50 | 0.20 | $200,000.00 | $40,000.00 |
| S-2 | TRASH RACK DOOR FRAMING MODIFICATIONS | | LS |
1.00
| 0.00 | 1.00 | $1,900.00 | $1,900.00 |