| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.95
| 0.83 | 0.12 | $10,000.00 | $1,200.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.95
| 0.90 | 0.05 | $35,000.00 | $1,750.00 |
| 6 | OFFICE FACILITIES | 6.00 | MTH |
5.75
| 5.50 | 0.25 | $3,000.00 | $750.00 |
| 9 | MAINTENANCE AND PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.66
| 0.33 | 0.33 | $6,000.00 | $1,980.00 |
| 10 | TREE ESTABLISHMENT BY TRUCK WATERING | 1.00 | LS |
0.90
| 0.60 | 0.30 | $8,000.00 | $2,400.00 |
| 15 | CONCRETE REMOVAL (NON-REINFORCED) | 472.00 | CY |
411.75
| 406.75 | 5.00 | $404.00 | $2,020.00 |
| 16 | UNCLASSIFIED EXCAVATION | 3,962.00 | CY |
2,722.00
| 2,247.55 | 474.45 | $100.00 | $47,445.00 |
| 17 | CRUSHED MISCELLANEOUS BASE | 2,581.00 | CY |
1,978.00
| 1,816.60 | 161.40 | $48.00 | $7,747.20 |
| 19 | AC PAVEMENT | 1,705.00 | TON |
1,471.25
| 890.35 | 580.90 | $219.00 | $127,217.10 |
| 20 | AC PAVEMENT(PATCH BACK) | 27.00 | TON |
26.50
| 24.25 | 2.25 | $219.00 | $492.75 |
| 21 | RECONSTRUCT MANHOLE | 11.00 | EA |
9.00
| 7.00 | 2.00 | $2,600.00 | $5,200.00 |
| 39 | CROSS GUTTER (MOD) | 83.00 | CY |
60.00
| 50.00 | 10.00 | $1,015.00 | $10,150.00 |
| 40 | METAL HAND RAILINGS PER STD PLAN 606 | 24.00 | LF |
1.00
| 0.00 | 1.00 | $300.00 | $300.00 |
| 41 | SALVAGE AND RECONSTRUCT EXISTING CONCRETE PAVERS | 1.00 | LS |
0.75
| 0.40 | 0.35 | $6,965.00 | $2,437.75 |
| 43 | FILTER FABRIC UNDER CONCRETE UNIT PAVERS | 798.00 | SF |
540.00
| 340.00 | 200.00 | $1.00 | $200.00 |
| 45 | 1/4" CRUSHED ROCK | 4.00 | CY |
4.00
| 0.00 | 4.00 | $275.00 | $1,100.00 |
| 46 | NO. 3 CONCRETE AGGREGATE | 15.00 | CY |
10.00
| 4.25 | 5.75 | $128.00 | $736.00 |
| 47 | WASHED CONCRETE SAND | 4.00 | CY |
4.00
| 1.50 | 2.50 | $310.00 | $775.00 |
| 49 | LANDSCAPING | 1.00 | LS |
0.80
| 0.65 | 0.15 | $30,100.00 | $4,515.00 |
| 55 | NO.2 GRAVEL | 10.00 | TON |
8.75
| 1.25 | 7.50 | $130.00 | $975.00 |
| 67 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 2,887.00 | LF |
2,887.00
| 0.00 | 2,887.00 | $26.00 | $75,062.00 |
| 86 | TYPE 332 CABINET | 1.00 | EA |
1.00
| 0.00 | 1.00 | $28,545.00 | $28,545.00 |
| 87 | TYPE 332 CABINET FOUNDATION | 1.00 | EA |
1.00
| 0.00 | 1.00 | $3,069.00 | $3,069.00 |
| 88 | TYPE 1 STANDARD | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,716.00 | $3,432.00 |
| 89 | TYPE 15 STANDARD | 4.00 | EA |
4.00
| 0.00 | 4.00 | $4,856.50 | $19,426.00 |
| 90 | TYPE 19 STANDARD | 1.00 | EA |
1.00
| 0.00 | 1.00 | $17,127.00 | $17,127.00 |
| 95 | 25' SIGNAL MAST ARM | 1.00 | EA |
1.00
| 0.00 | 1.00 | $4,857.00 | $4,857.00 |
| 102 | PEDESTRIAN PUSH BUTTON POST | 2.00 | EA |
2.00
| 0.00 | 2.00 | $973.50 | $1,947.00 |
| 111 | REMOVE STRIPING | 13,680.00 | LF |
3,000.00
| 0.00 | 3,000.00 | $1.70 | $5,100.00 |
| 112 | REMOVE PAVEMENT MARKINGS (THERMOPLASTIC) | 1,887.00 | SF |
400.00
| 0.00 | 400.00 | $3.00 | $1,200.00 |
| 122 | PAVEMENT MARKINGS (THERMOPLASTIC) | 2,641.00 | SF |
500.00
| 0.00 | 500.00 | $14.00 | $7,000.00 |
| 130 | PEDESTRIAN DIRECTIONAL SIGN PANELS | 32.00 | EA |
32.00
| 0.00 | 32.00 | $3,300.00 | $105,600.00 |
| 139 | TRAFFIC CONTROL | 1.00 | LS |
0.94
| 0.88 | 0.06 | $419,835.00 | $25,190.10 |
|