| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
2.00
| 0.00 | 2.00 | $500.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $10,000.00 | $2,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $50,000.00 | $10,000.00 |
| 7 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $20,000.00 | $4,000.00 |
| 8 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $5000) | 1.00 | LS |
1.00
| 0.50 | 0.50 | $5,000.00 | $2,500.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.20
| 0.00 | 0.20 | $40,000.00 | $8,000.00 |
| 10 | MOBILIZATION | 1.00 | LS |
0.95
| 0.50 | 0.45 | $750,000.00 | $337,500.00 |
| 12 | DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
0.40
| 0.20 | 0.20 | $50,000.00 | $10,000.00 |
| 13 | DEWATERING AND BYPASS (WITHIN INLET AND OUTLET WORKS AREA) | 1.00 | LS |
0.40
| 0.10 | 0.30 | $75,000.00 | $22,500.00 |
| 15 | BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
0.20
| 0.00 | 0.20 | $75,000.00 | $15,000.00 |
| 16 | BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
0.90
| 0.00 | 0.90 | $75,000.00 | $67,500.00 |
| 17 | BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY) | 1.00 | EA |
0.40
| 0.10 | 0.30 | $520,000.00 | $156,000.00 |
| 18 | BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY) | 1.00 | EA |
0.40
| 0.10 | 0.30 | $550,000.00 | $165,000.00 |
| 19 | BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY) | 1.00 | EA |
0.40
| 0.00 | 0.40 | $550,000.00 | $220,000.00 |
| 23 | STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
0.20
| 0.05 | 0.15 | $150,000.00 | $22,500.00 |
| 24 | STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
0.90
| 0.00 | 0.90 | $100,000.00 | $90,000.00 |
| 26 | STEEL DOORS - OUTLET STRUCTURES 2 AND 3 (ABRASIVELY BLAST AND COATING) | 2.00 | EA |
1.00
| 0.00 | 1.00 | $30,000.00 | $30,000.00 |
| 27 | TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 1 | 5,100.00 | SF |
510.00
| 255.00 | 255.00 | $250.00 | $63,750.00 |
| 28 | TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 2 | 1.00 | EA |
0.25
| 0.05 | 0.20 | $150,000.00 | $30,000.00 |
| 29 | TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 3 | 1.00 | EA |
0.50
| 0.00 | 0.50 | $250,000.00 | $125,000.00 |
| 32 | HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY) | 1.00 | EA |
0.25
| 0.00 | 0.25 | $200,000.00 | $50,000.00 |
| 33 | HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY) | 1.00 | EA |
0.25
| 0.10 | 0.15 | $200,000.00 | $30,000.00 |
| 34 | HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY) | 1.00 | EA |
0.25
| 0.00 | 0.25 | $200,000.00 | $50,000.00 |
| 35 | HYDRAULIC CYLINDER REFURBISHMENT - SLUICE GATE (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY) | 1.00 | EA |
0.25
| 0.10 | 0.15 | $200,000.00 | $30,000.00 |
| S-01 | DSC - CLEANING FOR BUTTERFLY 1, 2, CYL. 1 | | LS |
0.80
| 0.00 | 0.80 | $15,000.00 | $12,000.00 |
| S-02 | DSC - CLEANING AT OUTLET STRUCTURE 1, 2 | | LS |
1.00
| 0.00 | 1.00 | $17,280.00 | $17,280.00 |
|