Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.55
| 0.45 | 0.10 | $22,000.00 | $2,200.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $11,000.00 | $11,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.70
| 0.55 | 0.15 | $90,769.00 | $13,615.35 |
11 | CONCRETE REMOVAL (NON-REINFORCED) | 730.00 | CY |
714.10
| 545.80 | 168.30 | $360.00 | $60,588.00 |
13 | UNCLASSIFIED EXCAVATION | 1,835.00 | CY |
1,042.74
| 798.30 | 244.44 | $190.00 | $46,443.60 |
19 | CONCRETE SEDIMENT TRAP SPLASH PAD | 2.00 | EA |
2.00
| 0.00 | 2.00 | $5,200.00 | $10,400.00 |
21 | CRUSHED MISCELLANEOUS BASE | 1,157.00 | CY |
920.31
| 711.94 | 208.37 | $140.00 | $29,171.80 |
26 | AC PAVEMENT | 4,046.00 | TON |
58.74
| 30.67 | 28.07 | $125.00 | $3,508.75 |
27 | AC PAVEMENT(PATCH BACK) | 156.00 | TON |
89.18
| 71.45 | 17.73 | $300.00 | $5,319.00 |
33 | CURB DRAIN PER STD PLAN 150, N=1, CASE 3 INLET | 1.00 | EA |
1.00
| 0.00 | 1.00 | $1,700.00 | $1,700.00 |
41 | LOW CONCRETE RETAINING WALL | 47.00 | LF |
47.00
| 0.00 | 47.00 | $520.00 | $24,440.00 |
42 | PCC CURB, TYPE A1-6 | 149.00 | LF |
149.00
| 46.25 | 102.75 | $70.00 | $7,192.50 |
43 | PCC CURB, TYPE A1-8 | 181.00 | LF |
140.25
| 70.00 | 70.25 | $60.00 | $4,215.00 |
44 | PCC CURB & GUTTER, TYPE A2-6 | 597.00 | LF |
597.00
| 481.00 | 116.00 | $50.00 | $5,800.00 |
45 | PCC CURB & GUTTER, TYPE A2-8 | 1,516.00 | LF |
1,516.00
| 1,093.75 | 422.25 | $55.00 | $23,223.75 |
48 | LONGITUDINAL GUTTER | 1.00 | CY |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
49 | PCC WALK & DRIVEWAYS, 4" THICK | 12,226.00 | SF |
12,226.00
| 11,228.80 | 997.20 | $11.00 | $10,969.20 |
50 | PCC CURB RAMPS | 133.00 | CY |
133.00
| 93.31 | 39.69 | $1,180.00 | $46,834.20 |
52 | PCC, 4" THICK | 239.00 | SF |
239.00
| 0.00 | 239.00 | $15.00 | $3,585.00 |
55 | DETECTABLE WARNING SURFACE | 918.00 | SF |
825.00
| 519.00 | 306.00 | $55.00 | $16,830.00 |
56 | CROSS GUTTER | 104.00 | CY |
104.00
| 90.00 | 14.00 | $570.00 | $7,980.00 |
57 | CROSS GUTTER (MOD) | 93.00 | CY |
93.00
| 59.89 | 33.11 | $650.00 | $21,521.50 |
67 | 4" CONDUIT (SCH 80 PVC) | 175.00 | LF |
163.00
| 0.00 | 163.00 | $100.00 | $16,300.00 |
85 | TRAFFIC CONTROL | 1.00 | LS |
0.65
| 0.55 | 0.10 | $60,000.00 | $6,000.00 |
S-3 | ADDED WORK - SIDEWALK, C&G, DWAY | | T&M |
47,063.76
| 0.00 | 47,063.76 | $1.00 | $47,063.76 |
|