| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | TRAFFIC CONTROL | 1.00 | LS |
0.75
| 0.50 | 0.25 | $365,000.00 | $91,250.00 |
| 5 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.75
| 0.50 | 0.25 | $30,000.00 | $7,500.00 |
| 8 | CONSTRUCTION SCHEDULE (UPDATE) (2024) (STIPULATED UNIT PRICE OF $500/MTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 9 | IMPLEMENTATION OF BMPS (2024) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $20,000.00 | $20,000.00 |
| 11 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN (2024) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $10,000.00 | $10,000.00 |
| 12 | OFFICE FACILITIES (2024) | 5.00 | MTH |
3.00
| 2.00 | 1.00 | $12,000.00 | $12,000.00 |
| 13 | CLEARING AND GRUBBING (2024) | 34.00 | AC |
34.00
| 17.00 | 17.00 | $10,000.00 | $170,000.00 |
| 14 | WATER TRUCKS (2024) | 100.00 | DAYS |
70.00
| 27.00 | 43.00 | $1,100.00 | $47,300.00 |
| 15 | MOBILIZATION (2024) | 1.00 | LS |
0.95
| 0.75 | 0.20 | $605,000.00 | $121,000.00 |
| 17 | MAINTENANCE OF EXCLUSIONARY FENCE (2024) | 9,100.00 | LF |
9,100.00
| 1,820.00 | 7,280.00 | $2.50 | $18,200.00 |
| 18 | REMOVAL OF EXCLUSIONARY FENCE (2024) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $21,000.00 | $21,000.00 |
| 19 | SEPARATION OF ORGANIC MATERIAL AND TRASH (2024) | 1,400.00 | TON |
19.46
| 0.00 | 19.46 | $10.00 | $194.60 |
| 22 | TRANSPORTATION AND DISPOSAL OF SEDIMENT TO [SHELDON] (2024) | 187,500.00 | TON |
52,079.06
| 0.00 | 52,079.06 | $9.60 | $499,958.98 |
| 23 | RIPRAP (CLASS V) (2024) | 150.00 | CY |
150.00
| 0.00 | 150.00 | $170.00 | $25,500.00 |
| 24 | PORTABLE SCALES (2024) | 100.00 | DAYS |
68.00
| 24.00 | 44.00 | $1,500.00 | $66,000.00 |
| 25 | RESERVOIR EXCAVATION (2024) | 202,500.00 | TON |
86,268.06
| 36,811.50 | 49,456.56 | $4.50 | $222,554.52 |
| 26 | STREET SWEEPING (2024) | 100.00 | DAYS |
48.00
| 7.00 | 41.00 | $2,800.00 | $114,800.00 |
| 28 | MAINTENANCE OF TIRE WASH (2024) | 5.00 | MTH |
2.00
| 0.00 | 2.00 | $8,000.00 | $16,000.00 |
| 29 | REMOVAL OF TIRE WASH (2024) | 2.00 | EA |
2.00
| 0.00 | 2.00 | $5,000.00 | $10,000.00 |
| S-4 | SOIL TESTING FOR VULCAN | | LS |
1.00
| 0.00 | 1.00 | $21,387.66 | $21,387.66 |
| S-5 | 2024 SIDE SLOPE REPAIR | | LS |
1.00
| 0.00 | 1.00 | $30,327.29 | $30,327.29 |
|