| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 8.00 | MTH |
8.00
| 7.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.97
| 0.93 | 0.04 | $6,000.00 | $240.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.97
| 0.93 | 0.04 | $32,000.00 | $1,280.00 |
| 14 | REMOVE EXISTING CHAIN LINK FENCE | 30.00 | LF |
30.00
| 0.00 | 30.00 | $50.00 | $1,500.00 |
| 16 | UNCLASSIFIED EXCAVATION | 825.00 | CY |
900.00
| 893.00 | 7.00 | $240.00 | $1,680.00 |
| 17 | UNCLASSIFIED EXCAVATION (ROADWAY) | 9,513.00 | CY |
9,513.00
| 7,308.00 | 2,205.00 | $80.00 | $176,400.00 |
| 22 | COLD MILL AC PAVEMENT (> 1-1/2 - 3") | 1,085,013.00 | SF |
1,076,956.00
| 1,070,976.00 | 5,980.00 | $0.32 | $1,913.60 |
| 23 | COLD MILL AC PAVEMENT (> 3") | 81,043.00 | SF |
81,043.00
| 0.00 | 81,043.00 | $0.54 | $43,763.22 |
| 25 | AC PAVEMENT (SPEED CUSHION) | 91.00 | TON |
101.00
| 0.00 | 101.00 | $650.00 | $65,650.00 |
| 26 | RECONSTRUCT MANHOLE | 119.00 | EA |
86.20
| 32.70 | 53.50 | $2,000.00 | $107,000.00 |
| 28 | ASPHALT RUBBER HOT MIX | 10,446.00 | TON |
10,036.00
| 3,409.08 | 6,626.92 | $139.00 | $921,141.88 |
| 30 | CCPR AC PAVEMENT, 2.5" THICK | 129,630.00 | SY |
118,996.00
| 116,042.00 | 2,954.00 | $7.40 | $21,859.60 |
| 31 | CCPRACP MIX DESIGN, SAMPLING, AND TESTING (STIPULATED UNIT PRICE OF $10000) | 1.00 | LS |
0.90
| 0.85 | 0.05 | $10,000.00 | $500.00 |
| 49 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.77 | 0.13 | $473,000.00 | $61,490.00 |
| S-4 | CRUSHED MISCELLANEOUS BASE | | CY |
148.00
| 0.00 | 148.00 | $51.20 | $7,577.60 |
| S-5 | SUBGRADE PREPARATION (EAST/WEST) | | SF |
1,079,000.00
| 1,070,752.00 | 8,248.00 | $0.11 | $907.28 |
| S-6 | SUBGRADE PREPARATION (NORTH/SOUTH) | | SF |
87,500.00
| 0.00 | 87,500.00 | $0.27 | $23,625.00 |
|