| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 11.00 | MTH |
6.00
| 3.00 | 3.00 | $500.00 | $1,500.00 |
| 4 | MOBILIZATION | 1.00 | LS |
0.95
| 0.50 | 0.45 | $141,250.00 | $63,562.50 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.54
| 0.36 | 0.18 | $10,000.00 | $1,800.00 |
| 6 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.54
| 0.36 | 0.18 | $5,000.00 | $900.00 |
| 8 | CONCRETE REMOVAL (NON-REINFORCED) | 27.00 | CY |
27.00
| 0.00 | 27.00 | $420.00 | $11,340.00 |
| 15 | PCC CURB & GUTTER, TYPE A2-VAR | 198.00 | LF |
170.00
| 0.00 | 170.00 | $180.00 | $30,600.00 |
| 17 | PCC WALK & CURB RAMPS, 4" THICK | 1,296.00 | SF |
1,296.00
| 0.00 | 1,296.00 | $21.60 | $27,993.60 |
| 18 | DETECTABLE WARNING SURFACE | 139.00 | SF |
48.00
| 0.00 | 48.00 | $210.00 | $10,080.00 |
| 33 | TYPE III PULL BOX | 37.00 | EA |
19.00
| 18.00 | 1.00 | $1,100.00 | $1,100.00 |
| 38 | REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.) | 7.00 | EA |
5.00
| 0.00 | 5.00 | $800.00 | $4,000.00 |
| 39 | REMOVE TYPE 3 STANDARD (COMPLETE) (EXCL. FOUND.) | 2.00 | EA |
1.00
| 0.00 | 1.00 | $600.00 | $600.00 |
| 53 | REMOVE TYPE 1 FOUNDATION | 3.00 | EA |
3.00
| 0.00 | 3.00 | $1,300.00 | $3,900.00 |
| 54 | REMOVE TYPE 3 FOUNDATION | 2.00 | EA |
2.00
| 0.00 | 2.00 | $1,100.00 | $2,200.00 |
| 81 | TYPE 1 STANDARD | 4.00 | EA |
4.00
| 3.00 | 1.00 | $2,593.00 | $2,593.00 |
| 107 | COUNTDOWN PEDESTRIAN MODULE (COMPLETE) | 17.00 | EA |
15.00
| 6.00 | 9.00 | $1,343.00 | $12,087.00 |
| 108 | LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE) | 12.00 | EA |
3.00
| 0.00 | 3.00 | $1,343.00 | $4,029.00 |
| 132 | TRAFFIC CONTROL | 1.00 | LS |
0.54
| 0.36 | 0.18 | $88,884.00 | $15,999.12 |
| S-1 | TRENCH & RESTORATION | | T&M |
15,137.68
| 0.00 | 15,137.68 | $1.00 | $15,137.68 |
|