Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Olympic Boulevard TSSP - Indiana Street to Montebello Boulevard
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010287
Federal Number(s): None
Original Contract: $2,514,601.72
Awarded: 6/22/2023
Period Ending: 9/20/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 6.00 3.003.00$500.00$1,500.00
4MOBILIZATION1.00LS 0.95 0.500.45$141,250.00$63,562.50
5IMPLEMENTATION OF BMPS1.00LS 0.54 0.360.18$10,000.00$1,800.00
6IMPLEMENTATION OF THE LTWHP1.00LS 0.54 0.360.18$5,000.00$900.00
8CONCRETE REMOVAL (NON-REINFORCED)27.00CY 27.00 0.0027.00$420.00$11,340.00
15PCC CURB & GUTTER, TYPE A2-VAR198.00LF 170.00 0.00170.00$180.00$30,600.00
17PCC WALK & CURB RAMPS, 4" THICK1,296.00SF 1,296.00 0.001,296.00$21.60$27,993.60
18DETECTABLE WARNING SURFACE139.00SF 48.00 0.0048.00$210.00$10,080.00
33TYPE III PULL BOX37.00EA 19.00 18.001.00$1,100.00$1,100.00
38REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.)7.00EA 5.00 0.005.00$800.00$4,000.00
39REMOVE TYPE 3 STANDARD (COMPLETE) (EXCL. FOUND.)2.00EA 1.00 0.001.00$600.00$600.00
53REMOVE TYPE 1 FOUNDATION3.00EA 3.00 0.003.00$1,300.00$3,900.00
54REMOVE TYPE 3 FOUNDATION2.00EA 2.00 0.002.00$1,100.00$2,200.00
81TYPE 1 STANDARD4.00EA 4.00 3.001.00$2,593.00$2,593.00
107COUNTDOWN PEDESTRIAN MODULE (COMPLETE)17.00EA 15.00 6.009.00$1,343.00$12,087.00
108LED COUNTDOWN PEDESTRIAN HEAD (COMPLETE)12.00EA 3.00 0.003.00$1,343.00$4,029.00
132TRAFFIC CONTROL1.00LS 0.54 0.360.18$88,884.00$15,999.12
S-1TRENCH & RESTORATION T&M 15,137.68 0.0015,137.68$1.00$15,137.68

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,195,006.14 $985,584.24 $209,421.90
Retained $59,750.31 $49,279.21 $10,471.10
Deducted $0.00 $0.00 $0.00
Due $1,135,255.83 $936,305.03 $198,950.80