| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
2.00
| 1.00 | 1.00 | $1,500.00 | $1,500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.60
| 0.20 | 0.40 | $16,000.00 | $6,400.00 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.50 | 0.50 | $168,000.00 | $84,000.00 |
| 9 | CONCRETE REMOVAL (NON-REINFORCED) | 242.00 | CY |
143.00
| 40.00 | 103.00 | $250.00 | $25,750.00 |
| 11 | UNCLASSIFIED EXCAVATION | 1,463.00 | CY |
636.00
| 420.00 | 216.00 | $195.00 | $42,120.00 |
| 12 | CRUSHED MISCELLANEOUS BASE | 908.00 | CY |
474.00
| 296.00 | 178.00 | $130.00 | $23,140.00 |
| 15 | AC PAVEMENT(PATCH BACK) | 49.00 | TON |
25.00
| 0.00 | 25.00 | $430.00 | $10,750.00 |
| 17 | PCC PAVEMENT (HIGH EARLY STRENGTH) | 449.00 | CY |
392.00
| 258.00 | 134.00 | $930.00 | $124,620.00 |
| 19 | PCC CURB & GUTTER, TYPE A2-8 | 438.00 | LF |
296.00
| 175.00 | 121.00 | $82.00 | $9,922.00 |
| 20 | PCC CURB & GUTTER, TYPE A2-VAR | 215.00 | LF |
188.00
| 115.00 | 73.00 | $83.00 | $6,059.00 |
| 22 | PCC WALK & DRIVEWAYS, 4" THICK | 5,505.00 | SF |
3,355.00
| 1,898.00 | 1,457.00 | $13.00 | $18,941.00 |
| 23 | PCC CURB RAMPS | 23.00 | CY |
15.61
| 8.20 | 7.41 | $1,100.00 | $8,151.00 |
| 25 | DETECTABLE WARNING SURFACE | 195.00 | SF |
105.00
| 60.00 | 45.00 | $49.00 | $2,205.00 |
| 31 | 2" CONDUIT (SCH 80 PVC) | 70.00 | LF |
21.00
| 0.00 | 21.00 | $110.00 | $2,310.00 |
| 63 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.20 | 0.40 | $143,000.00 | $57,200.00 |
| 70 | NO. 6 PULL BOX | 19.00 | EA |
12.00
| 8.00 | 4.00 | $1,700.00 | $6,800.00 |