Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Cogswell Dam Inlet - Outlet Works Rehabilitation Project Phase 2
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001313
Federal Number(s): None
Original Contract: $7,493,500.00
Awarded: 5/7/2024
Period Ending: 9/30/2024
Board Accepted: 8/19/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 3.00 2.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.70 0.400.30$10,000.00$3,000.00
5IMPLEMENTATION OF BMPS1.00LS 0.70 0.400.30$50,000.00$15,000.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.70 0.400.30$20,000.00$6,000.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.60 0.200.40$40,000.00$16,000.00
13DEWATERING AND BYPASS (WITHIN INLET AND OUTLET WORKS AREA)1.00LS 0.60 0.400.20$75,000.00$15,000.00
14BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 1 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.25 0.200.05$75,000.00$3,750.00
15BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.90 0.200.70$75,000.00$52,500.00
16BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.95 0.900.05$75,000.00$3,750.00
18BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY)1.00EA 0.60 0.400.20$550,000.00$110,000.00
19BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY)1.00EA 0.75 0.400.35$550,000.00$192,500.00
21SLUICE GATE REFURBISHMENT (REMOVE, ABRASIVELY BLAST, CAVITATION FILLING, COATING, REINSTALL)1.00EA 0.60 0.200.40$500,000.00$200,000.00
22STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 1 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.25 0.200.05$125,000.00$6,250.00
23STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.90 0.200.70$150,000.00$105,000.00
24STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.95 0.900.05$100,000.00$5,000.00
26STEEL DOORS - OUTLET STRUCTURES 2 AND 3 (ABRASIVELY BLAST AND COATING)2.00EA 1.50 1.000.50$30,000.00$15,000.00
27TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 15,100.00SF 2,040.00 510.001,530.00$250.00$382,500.00
28TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 21.00EA 0.75 0.250.50$150,000.00$75,000.00
29TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 31.00EA 0.75 0.500.25$250,000.00$62,500.00
32HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.75 0.250.50$200,000.00$100,000.00
33HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.75 0.250.50$200,000.00$100,000.00
34HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.75 0.250.50$200,000.00$100,000.00
35HYDRAULIC CYLINDER REFURBISHMENT - SLUICE GATE (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.50 0.250.25$200,000.00$50,000.00
46STAND BY - (ENVIRONMENTAL EVENT), PER DAY10.00EA 1.00 0.001.00$15,000.00$15,000.00
S-04ACOYOTE TUNNEL - RAILING DISASSEMBLY AND RE-ASSEMBLY, PLATFORM INSTALLATION LS 0.80 0.000.80$45,500.00$36,400.00
S-09AOWNER TRAILER LS 0.60 0.000.60$30,000.00$18,000.00
S-11SLUICEGATE SHAFT FABRICATION AND INSTALL LS 0.50 0.000.50$13,000.00$6,500.00
S-13HYDRAULIC VALVE REPLACEMENT - EIGHT VALVES LS 0.75 0.000.75$11,547.00$8,660.25

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,066,590.25 $2,362,780.00 $1,703,810.25
Retained $203,329.51 $118,139.00 $85,190.51
Deducted $0.00 $0.00 $0.00
Due $3,863,260.74 $2,244,641.00 $1,618,619.74