| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.90 | 0.10 | $15,000.00 | $1,500.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $25,000.00 | $2,500.00 |
| 19 | AC PAVEMENT(LEVELING COURSE) | 1,973.00 | TON |
2,036.00
| 1,973.00 | 63.00 | $150.00 | $9,450.00 |
| 21 | DOUBLE ADJUST MANHOLE | 5.00 | EA |
1.00
| 0.00 | 1.00 | $1,500.00 | $1,500.00 |
| 28 | REINFORCED CONCRETE RETAINING WALL TYPE 7 | 15.00 | CY |
16.50
| 15.00 | 1.50 | $2,500.00 | $3,750.00 |
| 35 | PCC WALK & DRIVEWAYS, 4" THICK | 2,071.00 | SF |
2,247.00
| 2,071.00 | 176.00 | $13.00 | $2,288.00 |
| 40 | COMPOSITE TYPE 2 PULL BOX INCL COVER | 1.00 | EA |
1.00
| 0.00 | 1.00 | $2,300.00 | $2,300.00 |
| 42 | 2" CONDUIT (SCH 80 PVC) | 115.00 | LF |
50.00
| 35.00 | 15.00 | $120.00 | $1,800.00 |
| 44 | 2-PAIR DETECTOR LEAD-IN CABLE | 1,315.00 | LF |
1,315.00
| 0.00 | 1,315.00 | $5.00 | $6,575.00 |
| 45 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 2,014.00 | LF |
2,014.00
| 0.00 | 2,014.00 | $21.00 | $42,294.00 |
| 46 | DETAIL 9 (THERMOPLASTIC) | 13,095.00 | LF |
13,095.00
| 0.00 | 13,095.00 | $0.85 | $11,130.75 |
| 47 | DETAIL 22 (THERMOPLASTIC) | 2,330.00 | LF |
2,330.00
| 0.00 | 2,330.00 | $1.80 | $4,194.00 |
| 48 | DETAIL 29 (THERMOPLASTIC) | 1,712.00 | LF |
1,712.00
| 0.00 | 1,712.00 | $3.15 | $5,392.80 |
| 49 | DETAIL 32 (THERMOPLASTIC) | 1,226.00 | LF |
1,226.00
| 0.00 | 1,226.00 | $3.00 | $3,678.00 |
| 50 | DETAIL 37B (THERMOPLASTIC) | 1,443.00 | LF |
1,443.00
| 0.00 | 1,443.00 | $2.15 | $3,102.45 |
| 51 | DETAIL 38 (THERMOPLASTIC) | 2,408.00 | LF |
2,408.00
| 0.00 | 2,408.00 | $2.15 | $5,177.20 |
| 52 | DETAIL 40 (THERMOPLASTIC) | 656.00 | LF |
656.00
| 0.00 | 656.00 | $1.40 | $918.40 |
| 53 | DETAIL 41 (THERMOPLASTIC) | 126.00 | LF |
126.00
| 0.00 | 126.00 | $1.40 | $176.40 |
| 54 | PAVEMENT MARKINGS (THERMOPLASTIC) | 4,990.00 | SF |
5,495.00
| 0.00 | 5,495.00 | $7.35 | $40,388.25 |
| 55 | 6" STRIPING (THERMOPLASTIC) | 3,013.00 | LF |
3,013.00
| 0.00 | 3,013.00 | $0.85 | $2,561.05 |
| 56 | 12" STRIPING (THERMOPLASTIC) | 620.00 | LF |
683.00
| 0.00 | 683.00 | $4.30 | $2,936.90 |
| 57 | REMOVE STRIPING AND MARKINGS (THERMOPLASTIC) | 381.00 | SF |
407.00
| 0.00 | 407.00 | $8.90 | $3,622.30 |
| 58 | INSTALL FIRE HYDRANT LOCATION RPM | 11.00 | EA |
11.00
| 0.00 | 11.00 | $30.00 | $330.00 |
| 59 | SIGN POST (ROADSIDE SIGN) | 2.00 | EA |
3.00
| 0.00 | 3.00 | $400.00 | $1,200.00 |
| 60 | SIGN PANEL | 2.00 | EA |
5.00
| 0.00 | 5.00 | $130.00 | $650.00 |
| 61 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.90 | 0.10 | $200,000.00 | $20,000.00 |
| 68 | CONSTRUCT AND REMOVE SILT FENCE | 60.00 | LF |
60.00
| 0.00 | 60.00 | $30.00 | $1,800.00 |
| 75 | FURNISH AND PLANT 1 GALLON SHRUB | 42.00 | EA |
46.00
| 42.00 | 4.00 | $70.00 | $280.00 |
| 76 | 90 DAY PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| S-2 | RELOCATE TS PB AT ALVERN ST. | | T&M |
29,807.43
| 0.00 | 29,807.43 | $1.00 | $29,807.43 |
| S-4 | PAVEMENT FABRIC REMOVAL | | LS |
1.00
| 0.00 | 1.00 | $10,088.93 | $10,088.93 |
| S-5 | HOMELESS ENCAMPMENT REMOVAL EFFORTS | | LS |
1.00
| 0.00 | 1.00 | $19,975.27 | $19,975.27 |
|