| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.75
| 0.50 | 0.25 | $25,000.00 | $6,250.00 |
| 8 | MOBILIZATION | 1.00 | LS |
0.75
| 0.50 | 0.25 | $120,000.00 | $30,000.00 |
| 12 | TRAFFIC CONTROL | 1.00 | LS |
0.60
| 0.50 | 0.10 | $20,000.00 | $2,000.00 |
| 15 | FURNISH AND PLANT 24" BOX TREE | 62.00 | EA |
43.00
| 0.00 | 43.00 | $275.00 | $11,825.00 |
| 16 | LANDSCAPING | 1.00 | LS |
0.30
| 0.15 | 0.15 | $253,000.00 | $37,950.00 |
| 24 | DECOMPOSED GRANITE, 4" THICK | 22,696.00 | SF |
9,069.00
| 0.00 | 9,069.00 | $5.25 | $47,612.25 |
| S-4 | BEST MANAGEMENT PRACTICES | | T&M |
15,000.00
| 5,700.00 | 9,300.00 | $1.00 | $9,300.00 |
| S-5 | CRUSHED MISCELLANEOUS BASE | | CY |
72.00
| 0.00 | 72.00 | $168.00 | $12,096.00 |