Progress Payment 6
Project Name: San Gabriel Valley Traffic Signal Safety Project Group I
Contractor: Elecnor Belco Electric, Inc.
14320 Albers Way
Chino, CA 91710
Project ID: TDS0001707
Federal Number(s): HSIPL-5953 (752)
Original Contract: $1,451,750.00
Awarded: 7/11/2023
Period Ending: 10/21/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4IMPLEMENTATION OF BMPS1.00LS 1.00 0.950.05$3,000.00$150.00
6SALVAGE EQUIPMENT1.00LS 1.00 0.001.00$10,000.00$10,000.00
203" CONDUIT (SCH 80 PVC)815.00LF 1,018.75 1,018.500.25$76.00$19.00
29INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT80.00LF 80.00 0.0080.00$19.00$1,520.00
32REMOVE EXISTING DLC785.00LF 785.00 0.00785.00$2.00$1,570.00
52SWITCH PACK22.00EA 22.00 0.0022.00$219.00$4,818.00
53PED ISOLATION MODULE6.00EA 6.00 0.006.00$277.00$1,662.00
542-CHANNEL ILD SENSOR UNIT6.00EA 6.00 0.006.00$452.00$2,712.00
55GPS UTB UNIT AND ANTENNA3.00EA 3.00 0.003.00$1,800.00$5,400.00
80PEDESTRIAN PUSH BUTTON15.00EA 15.00 0.0015.00$296.00$4,440.00
81PEDESTRIAN PUSH BUTTON PLATE15.00EA 15.00 0.0015.00$193.00$2,895.00
854-CAMERA VIDEO DETECTION SYSTEM (COMPLETE)1.00EA 1.00 0.001.00$50,100.00$50,100.00
864-CAMERA VIDEO/RADAR DETECTION SYSTEM (COMPLETE)2.00EA 2.00 0.002.00$48,200.00$96,400.00
87CAMERA MOUNT EXTENSION11.00EA 11.00 0.0011.00$174.00$1,914.00
90DETAIL 38 (THERMOPLASTIC)410.00LF 410.00 0.00410.00$3.00$1,230.00
91DETAIL 38A (THERMOPLASTIC)50.00LF 50.00 0.0050.00$3.00$150.00
92DETAIL 39 (THERMOPLASTIC)10.00LF 10.00 0.0010.00$3.00$30.00
934" STRIPING (THERMOPLASTIC)400.00LF 400.00 0.00400.00$2.60$1,040.00
9412" STRIPING (THERMOPLASTIC)420.00LF 395.00 0.00395.00$5.70$2,251.50
9524" STRIPING (THERMOPLASTIC)728.00LF 728.00 0.00728.00$11.00$8,008.00
9624" STRIPING (THERMOPLASTIC)1,618.00LF 1,618.00 0.001,618.00$11.00$17,798.00
97PAVEMENT MARKINGS (THERMOPLASTIC)162.00SF 162.00 0.00162.00$8.50$1,377.00
98REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)165.00SF 105.00 0.00105.00$10.00$1,050.00
99REMOVE STRIPING2,772.00LF 1,759.00 0.001,759.00$6.00$10,554.00
100SIGN PANEL4.00EA 4.00 0.004.00$390.00$1,560.00
104TRAFFIC CONTROL1.00LS 1.00 0.900.10$70,000.00$7,000.00
105CHANGEABLE MESSAGE SIGN (EACH)6.00MTH 6.00 5.001.00$2,800.00$2,800.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,479,789.29 $1,241,340.79 $238,448.50
Retained $73,989.46 $62,067.03 $11,922.43
Deducted $0.00 $0.00 $0.00
Due $1,405,799.83 $1,179,273.76 $226,526.07