Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: East Los Angeles - Cesar E Chavez Avenue
Contractor: Excel Paving Company
2230 Lemon Avenue
Long Beach, CA 90806-5195
Project ID: RMD4102001
Federal Number(s): None
Original Contract: $4,278,695.60
Awarded: 8/16/2023
Period Ending: 10/4/2024
Board Accepted: 2/24/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
19DOUBLE ADJUST MANHOLE52.00EA 52.00 26.0026.00$1,000.00$26,000.00
432-PAIR DETECTOR LEAD-IN CABLE1,300.00LF 1,300.00 0.001,300.00$3.00$3,900.00
44INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT3,967.00LF 3,967.00 0.003,967.00$21.00$83,307.00
77DETAIL 8 (THERMOPLASTIC)6,963.00LF 6,963.00 0.006,963.00$1.00$6,963.00
78DETAIL 9 (THERMOPLASTIC)5,751.00LF 5,575.00 0.005,575.00$1.10$6,132.50
79DETAIL 21 (THERMOPLASTIC)4,945.00LF 4,945.00 0.004,945.00$1.30$6,428.50
80DETAIL 22 (THERMOPLASTIC)3,328.00LF 3,328.00 0.003,328.00$1.40$4,659.20
81DETAIL 28 (THERMOPLASTIC)230.00LF 230.00 0.00230.00$4.00$920.00
82DETAIL 29 (THERMOPLASTIC)152.00LF 144.00 0.00144.00$4.00$576.00
83DETAIL 31 (THERMOPLASTIC)487.00LF 459.00 0.00459.00$4.00$1,836.00
84DETAIL 38 (THERMOPLASTIC)264.00LF 264.00 0.00264.00$1.20$316.80
85DETAIL 38A (THERMOPLASTIC)985.00LF 784.00 0.00784.00$1.10$862.40
86DETAIL 40 (THERMOPLASTIC)110.00LF 108.00 0.00108.00$5.00$540.00
87DETAIL 41 (THERMOPLASTIC)36.00LF 36.00 0.0036.00$5.00$180.00
88PAVEMENT MARKINGS (THERMOPLASTIC)1,615.00SF 1,615.00 0.001,615.00$7.00$11,305.00
896" STRIPING (THERMOPLASTIC)3,111.00LF 3,111.00 0.003,111.00$1.00$3,111.00
9012" STRIPING (THERMOPLASTIC)1,297.00LF 1,297.00 0.001,297.00$4.00$5,188.00
9124" STRIPING (THERMOPLASTIC)6,809.00LF 6,809.00 0.006,809.00$8.00$54,472.00
93INSTALL FIRE HYDRANT LOCATION RPM52.00EA 27.00 0.0027.00$15.00$405.00
94SIGN PANEL2.00EA 1.00 0.001.00$250.00$250.00
95REMOVE SIGN2.00EA 1.00 0.001.00$75.00$75.00
S-1TEMPORARY TRAFFIC SIGNAL PLAN T&M 32,478.70 0.0032,478.70$1.00$32,478.70

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,261,885.43 $4,011,979.33 $249,906.10
Retained $213,094.29 $200,598.97 $12,495.32
Deducted $0.00 $0.00 $0.00
Due $4,048,791.14 $3,811,380.36 $237,410.78



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.