Los Angeles County Public Works
Project Management Division III
Progress Payment 4
Project Name: Cogswell Dam Inlet - Outlet Works Rehabilitation Project Phase 2
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001313
Federal Number(s): None
Original Contract: $7,493,500.00
Awarded: 5/7/2024
Period Ending: 10/31/2024
Board Accepted: 8/19/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)6.00MTH 4.00 3.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.700.30$10,000.00$3,000.00
5IMPLEMENTATION OF BMPS1.00LS 0.95 0.700.25$50,000.00$12,500.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.95 0.700.25$20,000.00$5,000.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.80 0.600.20$40,000.00$8,000.00
10MOBILIZATION1.00LS 1.00 0.950.05$750,000.00$37,500.00
12DISPOSAL OF LBP/LCP WASTE1.00LS 0.50 0.400.10$50,000.00$5,000.00
14BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 1 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 1.00 0.250.75$75,000.00$56,250.00
15BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 1.00 0.900.10$75,000.00$7,500.00
16BV STEEL DISK AND BODY REFURBISHMENT - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 1.00 0.950.05$75,000.00$3,750.00
17BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY)1.00EA 0.90 0.400.50$520,000.00$260,000.00
18BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY)1.00EA 0.90 0.600.30$550,000.00$165,000.00
19BV DISC SEAT AND CLAMP RING ASSEMBLY REPLACEMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, FABRICATION, RE-ASSEMBLY)1.00EA 0.90 0.750.15$550,000.00$82,500.00
20BV DISC PERFORATION REPAIRS24.00EA 24.00 0.0024.00$12,500.00$300,000.00
21SLUICE GATE REFURBISHMENT (REMOVE, ABRASIVELY BLAST, CAVITATION FILLING, COATING, REINSTALL)1.00EA 0.90 0.600.30$500,000.00$150,000.00
22STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 1 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.95 0.250.70$125,000.00$87,500.00
23STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 0.95 0.900.05$150,000.00$7,500.00
24STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 3 (ABRASIVELY BLAST, CAVITATION FILLING, COATING)1.00EA 1.00 0.950.05$100,000.00$5,000.00
25STEEL LINER REHABILITATION - SLUICE GATE (ABRASIVELY BLAST, CAVITATION FILLING, COATING)500.00SF 425.00 0.00425.00$200.00$85,000.00
26STEEL DOORS - OUTLET STRUCTURES 2 AND 3 (ABRASIVELY BLAST AND COATING)2.00EA 2.00 1.500.50$30,000.00$15,000.00
27TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 15,100.00SF 4,590.00 2,040.002,550.00$250.00$637,500.00
28TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 21.00EA 0.95 0.750.20$150,000.00$30,000.00
29TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 31.00EA 1.00 0.750.25$250,000.00$62,500.00
32HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.90 0.750.15$200,000.00$30,000.00
33HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 2 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.90 0.750.15$200,000.00$30,000.00
34HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 3 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 0.90 0.750.15$200,000.00$30,000.00
35HYDRAULIC CYLINDER REFURBISHMENT - SLUICE GATE (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY)1.00EA 1.00 0.500.50$200,000.00$100,000.00
36FIELD OPERATIONAL TESTING - BUTTERFLY VALVE 11.00EA 1.00 0.001.00$25,000.00$25,000.00
37FIELD OPERATIONAL TESTING - BUTTERFLY VALVE 21.00EA 1.00 0.001.00$25,000.00$25,000.00
38FIELD OPERATIONAL TESTING - BUTTERFLY VALVE 31.00EA 1.00 0.001.00$25,000.00$25,000.00
39FIELD OPERATIONAL TESTING - SLUICE GATE1.00EA 1.00 0.001.00$25,000.00$25,000.00
44SITE RESTORATION1.00LS 0.75 0.000.75$40,000.00$30,000.00
45DEMOBILIZATION1.00LS 0.90 0.000.90$50,000.00$45,000.00
S-01DSC - CLEANING FOR BUTTERFLY 1, 2, CYL. 1 LS 1.00 0.800.20$15,000.00$3,000.00
S-04ACOYOTE TUNNEL - RAILING DISASSEMBLY AND RE-ASSEMBLY, PLATFORM INSTALLATION LS 1.00 0.800.20$45,500.00$9,100.00
S-09AOWNER TRAILER LS 1.00 0.600.40$30,000.00$12,000.00
S-11SLUICEGATE SHAFT FABRICATION AND INSTALL LS 1.00 0.500.50$13,000.00$6,500.00
S-13HYDRAULIC VALVE REPLACEMENT - EIGHT VALVES LS 1.00 0.750.25$11,547.00$2,886.75
S-15CYLINDER 1, 2, 3 - HYDRAULIC LINE MODIFICATION LS 1.00 0.001.00$47,689.00$47,689.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $6,539,266.00 $4,066,590.25 $2,472,675.75
Retained $326,963.30 $203,329.51 $123,633.79
Deducted $0.00 $0.00 $0.00
Due $6,212,302.70 $3,863,260.74 $2,349,041.96