Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.65 | 0.25 | $22,000.00 | $5,500.00 |
7 | OFFICE FACILITIES | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $11,000.00 | $11,000.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
0.95
| 0.80 | 0.15 | $90,769.00 | $13,615.35 |
13 | UNCLASSIFIED EXCAVATION | 1,835.00 | CY |
1,442.80
| 1,242.80 | 200.00 | $190.00 | $38,000.00 |
14 | UNCLASSIFIED EXCAVATION (ROADWAY) | 5,990.00 | CY |
5,990.00
| 2,246.00 | 3,744.00 | $90.00 | $336,960.00 |
18 | STABILIZATION GEOTEXTILE | 1,159.00 | SY |
801.00
| 401.00 | 400.00 | $12.00 | $4,800.00 |
20 | CRUSHED AGGREGATE BASE | 8.00 | CY |
4.40
| 0.00 | 4.40 | $350.00 | $1,540.00 |
21 | CRUSHED MISCELLANEOUS BASE | 1,157.00 | CY |
1,143.25
| 1,032.00 | 111.25 | $140.00 | $15,575.00 |
22 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 28,089.00 | SY |
24,429.00
| 14,223.50 | 10,205.50 | $9.00 | $91,849.50 |
23 | PORTLAND CEMENT FOR CSPB | 552.00 | TON |
194.30
| 114.87 | 79.43 | $220.00 | $17,474.60 |
24 | PRIME/TACK COAT FOR CSPB | 5,617.00 | GAL |
2,921.30
| 1,821.30 | 1,100.00 | $10.00 | $11,000.00 |
26 | AC PAVEMENT | 4,046.00 | TON |
2,490.70
| 2,071.50 | 419.20 | $125.00 | $52,400.00 |
27 | AC PAVEMENT(PATCH BACK) | 156.00 | TON |
89.20
| 89.18 | 0.02 | $300.00 | $6.00 |
28 | RECONSTRUCT MANHOLE | 38.00 | EA |
10.00
| 7.00 | 3.00 | $2,300.00 | $6,900.00 |
29 | PCC PAVEMENT | 300.00 | CY |
214.50
| 125.50 | 89.00 | $450.00 | $40,050.00 |
30 | ASPHALT RUBBER HOT MIX | 1,888.00 | TON |
1,218.30
| 0.00 | 1,218.30 | $160.00 | $194,928.00 |
59 | METAL HAND RAILINGS PER STD PLAN 606 | 42.00 | LF |
34.00
| 22.00 | 12.00 | $400.00 | $4,800.00 |
85 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.75 | 0.15 | $60,000.00 | $9,000.00 |
|