Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 11.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.75
| 0.40 | 0.35 | $20,000.00 | $7,000.00 |
7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.75
| 0.40 | 0.35 | $40,000.00 | $14,000.00 |
9 | OFFICE FACILITIES | 12.00 | MTH |
6.00
| 5.00 | 1.00 | $7,500.00 | $7,500.00 |
12 | CONCRETE REMOVAL (NON-REINFORCED) | 297.00 | CY |
342.00
| 318.00 | 24.00 | $375.00 | $9,000.00 |
13 | UNCLASSIFIED EXCAVATION | 352.00 | CY |
352.00
| 244.03 | 107.97 | $250.00 | $26,992.50 |
14 | UNCLASSIFIED EXCAVATION (ROADWAY) | 2,063.00 | CY |
1,459.00
| 1,309.81 | 149.19 | $170.00 | $25,362.30 |
16 | PULVERIZED BASE MATERIAL, 6" THICK | 51,273.00 | SY |
30,786.00
| 23,920.57 | 6,865.43 | $2.00 | $13,730.86 |
18 | COLD MILL AC PAVEMENT (0 - 1-1/2") | 5,561.00 | SF |
5,561.00
| 0.00 | 5,561.00 | $2.00 | $11,122.00 |
19 | COLD MILL AC PAVEMENT (> 3") | 461,406.00 | SF |
294,208.10
| 278,896.10 | 15,312.00 | $0.60 | $9,187.20 |
20 | AC PAVEMENT | 8,700.00 | TON |
6,176.78
| 5,516.52 | 660.26 | $110.00 | $72,628.60 |
24 | RECONSTRUCT MANHOLE (SEWER) | 19.00 | EA |
11.00
| 3.00 | 8.00 | $2,500.00 | $20,000.00 |
25 | RECONSTRUCT MANHOLE (STORM DRAIN) | 13.00 | EA |
13.00
| 3.00 | 10.00 | $7,000.00 | $70,000.00 |
26 | DOUBLE ADJUST WATER VALVE FRAME AND COVER PER DETAIL A ON SHEET 3 | 35.00 | EA |
35.00
| 16.00 | 19.00 | $1,150.00 | $21,850.00 |
27 | PCC PAVEMENT | 161.00 | CY |
130.50
| 73.00 | 57.50 | $480.00 | $27,600.00 |
28 | ASPHALT RUBBER HOT MIX | 3,887.00 | TON |
2,497.87
| 611.07 | 1,886.80 | $140.00 | $264,152.00 |
31 | DRILL AND BOND DOWEL | 86.00 | LF |
86.00
| 0.00 | 86.00 | $80.00 | $6,880.00 |
34 | REMOVE AND REPLACE EXISTING CATCH BASIN GRATE(S) PER DETAIL D ON SHEET 15 | 31.00 | EA |
29.00
| 0.00 | 29.00 | $1,400.00 | $40,600.00 |
37 | LOCAL DEPRESSION PER STD PLAN 313-3, CASE D | 1.00 | EA |
1.00
| 0.00 | 1.00 | $6,000.00 | $6,000.00 |
41 | PCC CURB, TYPE A1-8 | 2.00 | LF |
2.00
| 0.00 | 2.00 | $300.00 | $600.00 |
42 | PCC CURB, TYPE A1-VAR | 109.00 | LF |
107.00
| 97.00 | 10.00 | $80.00 | $800.00 |
44 | PCC CURB & GUTTER, TYPE A2-8 | 590.00 | LF |
603.00
| 530.50 | 72.50 | $95.00 | $6,887.50 |
45 | PCC CURB & GUTTER, TYPE A2-8, W=VAR | 38.00 | LF |
38.00
| 15.00 | 23.00 | $180.00 | $4,140.00 |
46 | PCC CURB & GUTTER, TYPE A2-VAR | 751.00 | LF |
751.00
| 691.00 | 60.00 | $115.00 | $6,900.00 |
47 | PCC WALK & DRIVEWAYS, 4" THICK | 7,714.00 | SF |
8,228.00
| 7,258.00 | 970.00 | $11.00 | $10,670.00 |
49 | PCC WALK & DRIVEWAYS, 6" THICK | 746.00 | SF |
1,601.00
| 728.00 | 873.00 | $24.00 | $20,952.00 |
51 | DETECTABLE WARNING SURFACE | 529.00 | SF |
433.00
| 361.00 | 72.00 | $60.00 | $4,320.00 |
55 | 18" RCP, 1500 D | 52.00 | LF |
48.00
| 41.00 | 7.00 | $625.00 | $4,375.00 |
88 | REMOVE GPS UTB UNIT & ANTENNA | 1.00 | EA |
1.00
| 0.00 | 1.00 | $110.00 | $110.00 |
89 | TYPE 2070 CONTROLLER | 2.00 | EA |
2.00
| 1.00 | 1.00 | $13,200.00 | $13,200.00 |
90 | SWITCH PACK | 9.00 | EA |
7.00
| 1.00 | 6.00 | $50.00 | $300.00 |
114 | PEDESTRIAN PUSH BUTTON | 12.00 | EA |
12.00
| 11.00 | 1.00 | $400.00 | $400.00 |
118 | DETAIL 22 (THERMOPLASTIC) | 7,562.00 | LF |
4,527.00
| 2,331.00 | 2,196.00 | $1.65 | $3,623.40 |
119 | DETAIL 29 (THERMOPLASTIC) | 1,111.00 | LF |
150.00
| 0.00 | 150.00 | $3.50 | $525.00 |
121 | DETAIL 38 (THERMOPLASTIC) | 782.00 | LF |
250.00
| 100.00 | 150.00 | $3.75 | $562.50 |
125 | DETAIL 9 (THERMOPLASTIC) | 12,384.00 | LF |
9,444.00
| 2,824.00 | 6,620.00 | $1.00 | $6,620.00 |
128 | PAVEMENT MARKINGS (THERMOPLASTIC) | 4,996.00 | SF |
3,732.00
| 844.00 | 2,888.00 | $8.30 | $23,970.40 |
132 | CURB MARKINGS (ONE-COAT PAINT) | 733.00 | LF |
733.00
| 0.00 | 733.00 | $3.00 | $2,199.00 |
133 | REMOVE DETAIL 22 (THERMOPLASTIC) | 165.00 | LF |
165.00
| 0.00 | 165.00 | $5.00 | $825.00 |
134 | REMOVE DETAIL 9 (THERMOPLASTIC) | 195.00 | LF |
195.00
| 0.00 | 195.00 | $4.00 | $780.00 |
136 | REMOVE 4" STRIPING (THERMOPLASTIC) | 370.00 | LF |
250.00
| 0.00 | 250.00 | $4.00 | $1,000.00 |
139 | TRAFFIC CONTROL | 1.00 | LS |
0.68
| 0.45 | 0.23 | $360,000.00 | $82,800.00 |
S-9 | SCHEDULE REPHASING AT WEBSTER ELEMENTARY | | LS |
1.00
| 0.00 | 1.00 | $14,942.00 | $14,942.00 |
S-10 | WORK FOR TS POLE FOUNDATION CONFLICT | | LS |
1.00
| 0.00 | 1.00 | $19,404.00 | $19,404.00 |
S-18 | DETECTABLE WARNING SURFACE CONCRETE TRANSITION AREA | | LS |
1.00
| 0.00 | 1.00 | $14,898.42 | $14,898.42 |
S-21 | TRAFFIC CONTROL & TRAFFIC PLATES | | LS |
1.00
| 0.00 | 1.00 | $6,286.00 | $6,286.00 |
|