Los Angeles County Public Works
Project Management Division III
Progress Payment 6
Project Name: Project No 450 - Alamitos Bay Pump Station - Discharge Line Replacement
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: FCC0001218
Federal Number(s): None
Original Contract: $5,397,430.00
Awarded: 6/27/2023
Period Ending: 11/10/2024
Board Accepted: 5/13/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)4.00MTH 6.00 5.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.97 0.940.03$15,000.00$450.00
5IMPLEMENTATION OF BMPS1.00LS 0.97 0.940.03$45,000.00$1,350.00
14IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN1.00LS 0.97 0.940.03$15,000.00$450.00
18IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.97 0.940.03$6,000.00$180.00
21IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN1.00LS 1.00 0.940.06$5,500.00$330.00
23SHORING OF OPEN EXCAVATIONS1.00LS 1.00 0.900.10$20,000.00$2,000.00
24OFFICE FACILITIES4.00MTH 6.00 5.001.00$3,500.00$3,500.00
28UNCLASSIFIED EXCAVATION169.00CY 169.00 84.0085.00$200.00$17,000.00
31STRUCTURE BACKFILL36.00CY 36.00 0.0036.00$125.00$4,500.00
32CONSTRUCT AND REMOVE COFFERDAM1.00EA 0.80 0.600.20$1,639,519.00$327,903.80
33STRUCTURE CONCRETE23.00CY 23.00 19.004.00$6,722.00$26,888.00
34BAR REINFORCING STEEL (EPOXY-COATED)6,210.00LB 6,210.00 6,077.00133.00$8.50$1,130.50
35DRILL AND BOND DOWEL (EPOXY CARTRIDGE)88.00LF 79.57 67.3312.24$150.00$1,836.00
38EXHAUST PIPE SUPPORT1.00LS 1.00 0.001.00$1,800.00$1,800.00
40WARNING SIGN MOUNTING FRAME4.00EA 4.00 0.004.00$3,100.00$12,400.00
41DOORS, WINDOWS AND LOUVERS1.00LS 1.00 0.860.14$114,955.00$16,093.70
45STEEL ROOF PANEL1.00LS 1.00 0.750.25$107,549.00$26,887.25
47TEMPORARY BOATYARD1.00LS 0.70 0.660.04$67,580.00$2,703.20
49ROOF EXHAUST FAN1.00LS 1.00 0.150.85$35,200.00$29,920.00
51HDPE PIPES1.00LS 1.00 0.590.41$248,271.00$101,791.11
53RUBBER FLAPPER SWING CHECK VALVES1.00LS 1.00 0.100.90$316,000.00$284,400.00
54RESTRAINED FLANGE COUPLING ADAPTERS1.00LS 1.00 0.500.50$56,400.00$28,200.00
56OUTLET STRUCTURE WARNING SIGN LIGHTING1.00LS 1.00 0.001.00$154,055.00$154,055.00
58PAINT PUMP STATION EXTERIOR WALL1.00LS 1.00 0.001.00$15,120.00$15,120.00
63ELECTRICAL WORK1.00LS 0.65 0.470.18$527,783.00$95,000.94
64TRAFFIC CONTROL1.00LS 0.94 0.880.06$196,500.00$11,790.00
S-5CHECK VALVE CONCRETE PAD CHANGES LS 1.00 0.001.00$3,700.00$3,700.00
S-1330-INCH EXPANSION JOINT LS 1.00 0.001.00$24,800.00$24,800.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 32.00 0.0032.00$2,000.00 $64,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,836,748.83 $3,640,069.33 $1,196,679.50
Retained* $241,837.45 $182,003.48 $59,833.97
Deducted $71,400.00 $7,400.00 $64,000.00
Due $4,523,511.38 $3,450,665.85 $1,072,845.53



*This project has an escrow account.

Contact Office Engineer
Contractor Copy  