| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.97
| 0.94 | 0.03 | $15,000.00 | $450.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.97
| 0.94 | 0.03 | $45,000.00 | $1,350.00 |
| 14 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.97
| 0.94 | 0.03 | $15,000.00 | $450.00 |
| 18 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.97
| 0.94 | 0.03 | $6,000.00 | $180.00 |
| 21 | IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN | 1.00 | LS |
1.00
| 0.94 | 0.06 | $5,500.00 | $330.00 |
| 23 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $20,000.00 | $2,000.00 |
| 24 | OFFICE FACILITIES | 4.00 | MTH |
6.00
| 5.00 | 1.00 | $3,500.00 | $3,500.00 |
| 28 | UNCLASSIFIED EXCAVATION | 169.00 | CY |
169.00
| 84.00 | 85.00 | $200.00 | $17,000.00 |
| 31 | STRUCTURE BACKFILL | 36.00 | CY |
36.00
| 0.00 | 36.00 | $125.00 | $4,500.00 |
| 32 | CONSTRUCT AND REMOVE COFFERDAM | 1.00 | EA |
0.80
| 0.60 | 0.20 | $1,639,519.00 | $327,903.80 |
| 33 | STRUCTURE CONCRETE | 23.00 | CY |
23.00
| 19.00 | 4.00 | $6,722.00 | $26,888.00 |
| 34 | BAR REINFORCING STEEL (EPOXY-COATED) | 6,210.00 | LB |
6,210.00
| 6,077.00 | 133.00 | $8.50 | $1,130.50 |
| 35 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 88.00 | LF |
79.57
| 67.33 | 12.24 | $150.00 | $1,836.00 |
| 38 | EXHAUST PIPE SUPPORT | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,800.00 | $1,800.00 |
| 40 | WARNING SIGN MOUNTING FRAME | 4.00 | EA |
4.00
| 0.00 | 4.00 | $3,100.00 | $12,400.00 |
| 41 | DOORS, WINDOWS AND LOUVERS | 1.00 | LS |
1.00
| 0.86 | 0.14 | $114,955.00 | $16,093.70 |
| 45 | STEEL ROOF PANEL | 1.00 | LS |
1.00
| 0.75 | 0.25 | $107,549.00 | $26,887.25 |
| 47 | TEMPORARY BOATYARD | 1.00 | LS |
0.70
| 0.66 | 0.04 | $67,580.00 | $2,703.20 |
| 49 | ROOF EXHAUST FAN | 1.00 | LS |
1.00
| 0.15 | 0.85 | $35,200.00 | $29,920.00 |
| 51 | HDPE PIPES | 1.00 | LS |
1.00
| 0.59 | 0.41 | $248,271.00 | $101,791.11 |
| 53 | RUBBER FLAPPER SWING CHECK VALVES | 1.00 | LS |
1.00
| 0.10 | 0.90 | $316,000.00 | $284,400.00 |
| 54 | RESTRAINED FLANGE COUPLING ADAPTERS | 1.00 | LS |
1.00
| 0.50 | 0.50 | $56,400.00 | $28,200.00 |
| 56 | OUTLET STRUCTURE WARNING SIGN LIGHTING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $154,055.00 | $154,055.00 |
| 58 | PAINT PUMP STATION EXTERIOR WALL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $15,120.00 | $15,120.00 |
| 63 | ELECTRICAL WORK | 1.00 | LS |
0.65
| 0.47 | 0.18 | $527,783.00 | $95,000.94 |
| 64 | TRAFFIC CONTROL | 1.00 | LS |
0.94
| 0.88 | 0.06 | $196,500.00 | $11,790.00 |
| S-5 | CHECK VALVE CONCRETE PAD CHANGES | | LS |
1.00
| 0.00 | 1.00 | $3,700.00 | $3,700.00 |
| S-13 | 30-INCH EXPANSION JOINT | | LS |
1.00
| 0.00 | 1.00 | $24,800.00 | $24,800.00 |
|