Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Project No. 5241 - Reinforced Concrete Box Reconstruction
Contractor: GMZ Engineering, Inc.
5655 Lindero Canyon Road #430
Westlake Village, CA 91362
Project ID: FCC0001319
Federal Number(s): None
Original Contract: $8,032,540.00
Awarded: 4/17/2023
Period Ending: 11/14/2024
Board Accepted: 5/13/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 1.00 0.001.00$1,000.00$1,000.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.970.03$35,000.00$1,050.00
5IMPLEMENTATION OF BMPS1.00LS 1.00 0.970.03$35,000.00$1,050.00
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 1.00 0.970.03$35,000.00$1,050.00
27DEBRIS REMOVAL1.00LS 1.00 0.970.03$50,000.00$1,500.00
28PROTECTION FENCE, SHORT END PANEL10.00LF 10.00 0.0010.00$810.00$8,100.00
30PROTECTION FENCE, HIGH END PANEL15.00LF 15.00 0.0015.00$810.00$12,150.00
31STEEL WAVE PROTECTION BARRIER1.00LS 1.00 0.550.45$400,000.00$180,000.00
36RESTORATION OF BEACH GROUND SURFACE1.00LS 1.00 0.970.03$35,000.00$1,050.00
40TRAFFIC CONTROL1.00LS 1.00 0.970.03$50,000.00$1,500.00
S-14BOLT PROCUREMENT TIME EXTENSION WD 10.00 0.0010.00$0.00$0.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $8,871,100.00 $8,662,650.00 $208,450.00
Retained $443,555.00 $433,132.50 $10,422.50
Deducted $0.00 $0.00 $0.00
Due $8,427,545.00 $8,229,517.50 $198,027.50