| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 4.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.90
| 0.25 | 0.65 | $24,000.00 | $15,600.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.75 | 0.15 | $25,000.00 | $3,750.00 |
| 7 | OFFICE FACILITIES | 5.00 | MTH |
5.00
| 4.00 | 1.00 | $5,500.00 | $5,500.00 |
| 8 | MOBILIZATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $120,000.00 | $30,000.00 |
| 9 | CLEARING AND GRUBBING | 123,451.00 | SF |
123,451.00
| 71,272.00 | 52,179.00 | $0.70 | $36,525.30 |
| 10 | UNCLASSIFIED EXCAVATION | 1,809.00 | CY |
1,147.00
| 524.00 | 623.00 | $72.00 | $44,856.00 |
| 11 | UTILITY POTHOLES | 6.00 | EA |
6.00
| 4.00 | 2.00 | $1,000.00 | $2,000.00 |
| 12 | TRAFFIC CONTROL | 1.00 | LS |
0.90
| 0.60 | 0.30 | $20,000.00 | $6,000.00 |
| 13 | RIVER ROCK COBBLE | 35.00 | TON |
35.00
| 0.00 | 35.00 | $135.00 | $4,725.00 |
| 15 | FURNISH AND PLANT 24" BOX TREE | 62.00 | EA |
62.00
| 43.00 | 19.00 | $275.00 | $5,225.00 |
| 16 | LANDSCAPING | 1.00 | LS |
0.66
| 0.30 | 0.36 | $253,000.00 | $91,080.00 |
| 18 | IRRIGATION SYSTEM | 1.00 | LS |
0.66
| 0.25 | 0.41 | $252,000.00 | $103,320.00 |
| 20 | TRENCH AND BACKFILL IN PLANTING AREA FOR NEW IRRIGATION WIRES | 2,152.00 | LF |
2,098.00
| 1,500.00 | 598.00 | $2.75 | $1,644.50 |
| 21 | FURNISH AND INSTALL NEW IRRIGATION WIRES | 15,000.00 | LF |
11,257.00
| 10,000.00 | 1,257.00 | $0.25 | $314.25 |
| 25 | NO. 2 CONCRETE AGGREGATE | 81.00 | TON |
77.69
| 0.00 | 77.69 | $85.00 | $6,603.65 |
| 27 | ROUND CONCRETE PICNIC TABLE AND ROUND CONCRETE PICNIC TABLE ADA ACCESSIBLE | 16.00 | EA |
8.00
| 0.00 | 8.00 | $3,900.00 | $31,200.00 |
| 28 | CONCRETE TRASH RECEPTACLE | 8.00 | EA |
4.00
| 0.00 | 4.00 | $3,550.00 | $14,200.00 |
| 29 | DECORATIVE BOULDERS | 115.00 | EA |
115.00
| 55.00 | 60.00 | $185.00 | $11,100.00 |
| S-1 | DG MODIFICATION | | LS |
0.75
| 0.50 | 0.25 | $14,330.00 | $3,582.50 |
| S-3 | NEW ADA RAMPS | | LS |
1.00
| 0.00 | 1.00 | $82,500.00 | $82,500.00 |
| S-5 | CRUSHED MISCELLANEOUS BASE | | CY |
109.00
| 72.00 | 37.00 | $168.00 | $6,216.00 |
| S-6 | RELOCATION OF WATERLINE & DRIPLINE | | T&M |
19,682.00
| 0.00 | 19,682.00 | $1.00 | $19,682.00 |
|