Progress Payment 9
Project Name: East Los Angeles - Cesar E Chavez Avenue
Contractor: Excel Paving Company
2230 Lemon Avenue
Long Beach, CA 90806-5195
Project ID: RMD4102001
Federal Number(s): None
Original Contract: $4,278,695.60
Awarded: 8/16/2023
Period Ending: 12/6/2024
Board Accepted: 2/24/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
8CONCRETE REMOVAL (NON-REINFORCED)282.00CY 350.00 310.8139.19$450.00$17,635.50
11CRUSHED MISCELLANEOUS BASE482.00CY 570.00 547.0023.00$219.00$5,037.00
16AC PAVEMENT140.00TON 145.99 140.005.99$380.00$2,276.20
17AC PAVEMENT(PATCH BACK)38.00TON 58.64 50.008.64$295.00$2,548.80
28PCC CURB & GUTTER, TYPE A2-VAR586.00LF 748.83 736.0012.83$96.00$1,231.68
29PCC WALK, 4" THICK2,286.00SF 4,092.67 3,506.00586.67$15.00$8,800.05
44INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT3,967.00LF 4,017.00 3,967.0050.00$21.00$1,050.00
77DETAIL 8 (THERMOPLASTIC)6,963.00LF 6,583.00 6,963.00-380.00$1.00($380.00)
78DETAIL 9 (THERMOPLASTIC)5,751.00LF 5,572.00 5,575.00-3.00$1.10($3.30)
79DETAIL 21 (THERMOPLASTIC)4,945.00LF 5,037.00 4,945.0092.00$1.30$119.60
80DETAIL 22 (THERMOPLASTIC)3,328.00LF 3,330.00 3,328.002.00$1.40$2.80
81DETAIL 28 (THERMOPLASTIC)230.00LF 265.00 230.0035.00$4.00$140.00
84DETAIL 38 (THERMOPLASTIC)264.00LF 335.00 264.0071.00$1.20$85.20
88PAVEMENT MARKINGS (THERMOPLASTIC)1,615.00SF 1,646.00 1,615.0031.00$7.00$217.00
896" STRIPING (THERMOPLASTIC)3,111.00LF 3,453.00 3,111.00342.00$1.00$342.00
9012" STRIPING (THERMOPLASTIC)1,297.00LF 1,910.00 1,297.00613.00$4.00$2,452.00
9124" STRIPING (THERMOPLASTIC)6,809.00LF 7,959.50 6,809.001,150.50$8.00$9,204.00
92REMOVE STRIPING AND MARKINGS (PAINT)2,516.00SF 2,706.00 2,516.00190.00$3.00$570.00
S-6WATER VALVE ADJUSTMENTS LS 1.00 0.001.00$38,000.00$38,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,415,101.21 $4,325,772.68 $89,328.53
Retained $220,755.07 $216,288.66 $4,466.41
Deducted $0.00 $0.00 $0.00
Due $4,194,346.14 $4,109,484.02 $84,862.12