| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 8 | CONCRETE REMOVAL (NON-REINFORCED) | 282.00 | CY |
350.00
| 310.81 | 39.19 | $450.00 | $17,635.50 |
| 11 | CRUSHED MISCELLANEOUS BASE | 482.00 | CY |
570.00
| 547.00 | 23.00 | $219.00 | $5,037.00 |
| 16 | AC PAVEMENT | 140.00 | TON |
145.99
| 140.00 | 5.99 | $380.00 | $2,276.20 |
| 17 | AC PAVEMENT(PATCH BACK) | 38.00 | TON |
58.64
| 50.00 | 8.64 | $295.00 | $2,548.80 |
| 28 | PCC CURB & GUTTER, TYPE A2-VAR | 586.00 | LF |
748.83
| 736.00 | 12.83 | $96.00 | $1,231.68 |
| 29 | PCC WALK, 4" THICK | 2,286.00 | SF |
4,092.67
| 3,506.00 | 586.67 | $15.00 | $8,800.05 |
| 44 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 3,967.00 | LF |
4,017.00
| 3,967.00 | 50.00 | $21.00 | $1,050.00 |
| 77 | DETAIL 8 (THERMOPLASTIC) | 6,963.00 | LF |
6,583.00
| 6,963.00 | -380.00 | $1.00 | ($380.00) |
| 78 | DETAIL 9 (THERMOPLASTIC) | 5,751.00 | LF |
5,572.00
| 5,575.00 | -3.00 | $1.10 | ($3.30) |
| 79 | DETAIL 21 (THERMOPLASTIC) | 4,945.00 | LF |
5,037.00
| 4,945.00 | 92.00 | $1.30 | $119.60 |
| 80 | DETAIL 22 (THERMOPLASTIC) | 3,328.00 | LF |
3,330.00
| 3,328.00 | 2.00 | $1.40 | $2.80 |
| 81 | DETAIL 28 (THERMOPLASTIC) | 230.00 | LF |
265.00
| 230.00 | 35.00 | $4.00 | $140.00 |
| 84 | DETAIL 38 (THERMOPLASTIC) | 264.00 | LF |
335.00
| 264.00 | 71.00 | $1.20 | $85.20 |
| 88 | PAVEMENT MARKINGS (THERMOPLASTIC) | 1,615.00 | SF |
1,646.00
| 1,615.00 | 31.00 | $7.00 | $217.00 |
| 89 | 6" STRIPING (THERMOPLASTIC) | 3,111.00 | LF |
3,453.00
| 3,111.00 | 342.00 | $1.00 | $342.00 |
| 90 | 12" STRIPING (THERMOPLASTIC) | 1,297.00 | LF |
1,910.00
| 1,297.00 | 613.00 | $4.00 | $2,452.00 |
| 91 | 24" STRIPING (THERMOPLASTIC) | 6,809.00 | LF |
7,959.50
| 6,809.00 | 1,150.50 | $8.00 | $9,204.00 |
| 92 | REMOVE STRIPING AND MARKINGS (PAINT) | 2,516.00 | SF |
2,706.00
| 2,516.00 | 190.00 | $3.00 | $570.00 |
| S-6 | WATER VALVE ADJUSTMENTS | | LS |
1.00
| 0.00 | 1.00 | $38,000.00 | $38,000.00 |
|