| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.98
| 0.90 | 0.08 | $10,000.00 | $800.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.98
| 0.90 | 0.08 | $60,000.00 | $4,800.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.98
| 0.90 | 0.08 | $25,000.00 | $2,000.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP WASTE | 1.00 | LS |
1.00
| 0.66 | 0.34 | $90,000.00 | $30,600.00 |
| 11 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 0.90 | 0.10 | $25,000.00 | $2,500.00 |
| 15 | DEMOLITION | 1.00 | LS |
0.98
| 0.90 | 0.08 | $390,000.00 | $31,200.00 |
| 17 | MISCELLANEOUS MECHANICAL WORKS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $600,000.00 | $60,000.00 |
| 18 | FURNISH AND INSTALL SUBMERSIBLE PUMP AND ACCESSORIES | 1.00 | LS |
1.00
| 0.15 | 0.85 | $800,000.00 | $680,000.00 |
| 19 | FURNISH AND INSTALL SUMP PUMP AND ACCESSORIES | 1.00 | LS |
0.98
| 0.90 | 0.08 | $180,000.00 | $14,400.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
0.97
| 0.80 | 0.17 | $600,000.00 | $102,000.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
0.95
| 0.85 | 0.10 | $600,000.00 | $60,000.00 |
| 23 | ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION | 1.00 | LS |
0.95
| 0.85 | 0.10 | $600,000.00 | $60,000.00 |
| 29 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.85 | 0.15 | $200,000.00 | $30,000.00 |
| S-5 | REPLACE ENTRANCE DOOR FRAMES | | LS |
0.98
| 0.90 | 0.08 | $12,500.00 | $1,000.00 |
| S-8 | DISCHARGE PIPE HANGERS | | LS |
1.00
| 0.00 | 1.00 | $3,200.00 | $3,200.00 |
| S-9 | ADDITIONAL ASBESTOS REMOVAL | | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |