| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.50
| 0.00 | 0.50 | $10,000.00 | $5,000.00 |
| 7 | ENVIRONMENTAL AIR MONITORING | 1.00 | LS |
1.00
| 0.00 | 1.00 | $15,000.00 | $15,000.00 |
| 8 | PREPARATION OF SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 13 | OFFICE FACILITIES | 4.00 | MTH |
2.00
| 1.00 | 1.00 | $15,000.00 | $15,000.00 |
| 16 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.25 | 0.25 | $228,771.00 | $57,192.75 |
| 17 | FLASHING ARROW SIGN | 1.00 | LS |
0.50
| 0.25 | 0.25 | $5,000.00 | $1,250.00 |
| 18 | CHANGEABLE MESSAGE SIGN | 1.00 | LS |
0.50
| 0.25 | 0.25 | $50,000.00 | $12,500.00 |
| 27 | REMOVE DETAIL 9 (PAINT) | 1,933.00 | LF |
1,933.00
| 0.00 | 1,933.00 | $1.00 | $1,933.00 |
| 29 | REMOVE DETAIL 21 (YELLOW PAINT) | 204.00 | LF |
204.00
| 0.00 | 204.00 | $7.00 | $1,428.00 |
| 31 | REMOVE DETAIL 22 (YELLOW PAINT) | 674.00 | LF |
674.00
| 0.00 | 674.00 | $7.00 | $4,718.00 |
| 33 | REMOVE DETAIL 27B (PAINT) | 755.00 | LF |
755.00
| 0.00 | 755.00 | $3.00 | $2,265.00 |
| 35 | REMOVE DETAIL 29 (YELLOW PAINT) | 755.00 | LF |
380.00
| 0.00 | 380.00 | $7.00 | $2,660.00 |
| 37 | REMOVE 12" STRIPING (PAINT) | 415.00 | LF |
415.00
| 0.00 | 415.00 | $7.00 | $2,905.00 |
| 39 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DECK) | 358.00 | SF |
320.00
| 107.50 | 212.50 | $185.00 | $39,312.50 |
| 40 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (SIDEWALK) | 33.00 | SF |
26.00
| 13.00 | 13.00 | $685.00 | $8,905.00 |
| 41 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (BARRIER) | 73.00 | SF |
73.00
| 20.00 | 53.00 | $330.00 | $17,490.00 |
| 45 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (DIAPHRAGM) | 22.00 | SF |
22.00
| 20.00 | 2.00 | $1,350.00 | $2,700.00 |
| 46 | REMOVE UNSOUND CONCRETE, MAX 4" DEPTH (GIRDER) | 467.00 | SF |
467.00
| 395.00 | 72.00 | $235.00 | $16,920.00 |
| 47 | RAPID SETTING CONCRETE PATCH (DECK) | 358.00 | SF |
320.00
| 107.50 | 212.50 | $235.00 | $49,937.50 |
| 48 | REPAIR SPALLED CONCRETE (SIDEWALK) | 33.00 | SF |
26.00
| 13.00 | 13.00 | $715.00 | $9,295.00 |
| 49 | REPAIR SPALLED CONCRETE (BARRIER) | 73.00 | SF |
73.00
| 20.00 | 53.00 | $360.00 | $19,080.00 |
| 53 | REPAIR SPALLED CONCRETE (DIAPHRAGM) | 22.00 | SF |
22.00
| 20.00 | 2.00 | $1,365.00 | $2,730.00 |
| 54 | REPAIR SPALLED CONCRETE (GIRDER) | 467.00 | SF |
467.00
| 395.00 | 72.00 | $280.00 | $20,160.00 |
| 55 | PREPARE CONCRETE DECK SURFACE | 66,907.00 | SF |
66,907.00
| 0.00 | 66,907.00 | $1.00 | $66,907.00 |
| 56 | TREAT BRIDGE DECK | 66,907.00 | SF |
66,907.00
| 0.00 | 66,907.00 | $1.00 | $66,907.00 |
| 57 | BRIDGE DECK TREATMENT MATERIAL | 836.00 | GAL |
677.00
| 0.00 | 677.00 | $70.00 | $47,390.00 |
| 58 | CLEAN EXPANSION JOINT | 874.00 | LF |
584.00
| 0.00 | 584.00 | $30.00 | $17,520.00 |
| 59 | JOINT SEAL (MR 1/2") | 185.00 | LF |
80.00
| 0.00 | 80.00 | $120.00 | $9,600.00 |
| 62 | JOINT SEAL, TYPE AL | 504.00 | LF |
504.00
| 0.00 | 504.00 | $56.00 | $28,224.00 |
| S-1 | TC ON ROSECRANS/SGR BIKE PATH | | T&M |
4,172.20
| 0.00 | 4,172.20 | $1.00 | $4,172.20 |
|