Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.90 | 0.10 | $22,000.00 | $2,200.00 |
9 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.95 | 0.05 | $90,769.00 | $4,538.45 |
13 | UNCLASSIFIED EXCAVATION | 1,835.00 | CY |
1,582.50
| 1,442.80 | 139.70 | $190.00 | $26,543.00 |
18 | STABILIZATION GEOTEXTILE | 1,159.00 | SY |
999.25
| 801.00 | 198.25 | $12.00 | $2,379.00 |
22 | CEMENT STABILIZED PULVERIZED BASE, 8" THICK | 28,089.00 | SY |
27,880.11
| 24,429.00 | 3,451.11 | $9.00 | $31,059.99 |
23 | PORTLAND CEMENT FOR CSPB | 552.00 | TON |
227.07
| 194.30 | 32.77 | $220.00 | $7,209.40 |
24 | PRIME/TACK COAT FOR CSPB | 5,617.00 | GAL |
4,957.00
| 2,921.30 | 2,035.70 | $10.00 | $20,357.00 |
26 | AC PAVEMENT | 4,046.00 | TON |
4,046.00
| 2,490.70 | 1,555.30 | $125.00 | $194,412.50 |
28 | RECONSTRUCT MANHOLE | 38.00 | EA |
18.00
| 10.00 | 8.00 | $2,300.00 | $18,400.00 |
29 | PCC PAVEMENT | 300.00 | CY |
258.40
| 214.50 | 43.90 | $450.00 | $19,755.00 |
30 | ASPHALT RUBBER HOT MIX | 1,888.00 | TON |
1,888.00
| 1,218.30 | 669.70 | $160.00 | $107,152.00 |
50 | PCC CURB RAMPS | 133.00 | CY |
124.20
| 133.00 | -8.80 | $1,180.00 | ($10,384.00) |
69 | INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT | 500.00 | LF |
252.00
| 0.00 | 252.00 | $20.00 | $5,040.00 |
70 | DETAIL 2 (THERMOPLASTIC) | 2,330.00 | LF |
2,030.00
| 0.00 | 2,030.00 | $1.40 | $2,842.00 |
71 | DETAIL 22 (THERMOPLASTIC) | 1,740.00 | LF |
1,733.00
| 0.00 | 1,733.00 | $3.00 | $5,199.00 |
72 | DETAIL 32 (THERMOPLASTIC) | 790.00 | LF |
760.00
| 0.00 | 760.00 | $4.00 | $3,040.00 |
73 | DETAIL 38 (THERMOPLASTIC) | 430.00 | LF |
420.00
| 0.00 | 420.00 | $3.00 | $1,260.00 |
74 | PAVEMENT MARKINGS (THERMOPLASTIC) | 1,519.00 | SF |
1,519.00
| 0.00 | 1,519.00 | $18.00 | $27,342.00 |
75 | 12" STRIPING (THERMOPLASTIC) | 1,895.00 | LF |
722.00
| 0.00 | 722.00 | $4.00 | $2,888.00 |
76 | 24" STRIPING (THERMOPLASTIC) | 250.00 | LF |
850.00
| 0.00 | 850.00 | $8.00 | $6,800.00 |
77 | CURB MARKINGS (ONE-COAT PAINT) | 370.00 | LF |
195.00
| 0.00 | 195.00 | $3.00 | $585.00 |
78 | REMOVE PAVEMENT MARKINGS (PAINT) | 119.00 | SF |
1,088.00
| 0.00 | 1,088.00 | $8.00 | $8,704.00 |
79 | REMOVE 8" STRIPING (PAINT) | 600.00 | LF |
536.00
| 0.00 | 536.00 | $8.00 | $4,288.00 |
80 | INSTALL FIRE HYDRANT LOCATION RPM | 13.00 | EA |
13.00
| 0.00 | 13.00 | $20.00 | $260.00 |
81 | SIGN POST (ROADSIDE SIGN) | 15.00 | EA |
15.00
| 0.00 | 15.00 | $550.00 | $8,250.00 |
82 | SIGN PANEL | 32.00 | EA |
23.00
| 0.00 | 23.00 | $300.00 | $6,900.00 |
83 | RELOCATE SIGN | 6.00 | EA |
6.00
| 0.00 | 6.00 | $430.00 | $2,580.00 |
84 | REMOVE SIGN | 7.00 | EA |
7.00
| 0.00 | 7.00 | $250.00 | $1,750.00 |
85 | TRAFFIC CONTROL | 1.00 | LS |
1.00
| 0.90 | 0.10 | $60,000.00 | $6,000.00 |
86 | FURNISH AND PLANT 24" BOX TREE | 5.00 | EA |
5.00
| 1.00 | 4.00 | $900.00 | $3,600.00 |
87 | DECOMPOSED GRANITE, 3" THICK | 72.00 | SF |
72.00
| 0.00 | 72.00 | $5.00 | $360.00 |
88 | TREE WELL AND COVER PER STD PLAN 519, TYPE 1 | 4.00 | EA |
4.00
| 0.00 | 4.00 | $6,200.00 | $24,800.00 |
89 | LANDSCAPING | 1.00 | LS |
1.00
| 0.25 | 0.75 | $10,000.00 | $7,500.00 |
90 | 90 DAY LANDSCAPE PLANT ESTABLISHMENT PERIOD | 1.00 | LS |
0.25
| 0.00 | 0.25 | $4,500.00 | $1,125.00 |
|