| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.985
| 0.97 | 0.015 | $15,000.00 | $225.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.985
| 0.97 | 0.015 | $45,000.00 | $675.00 |
| 9 | REMOVAL OF TEMPORARY SOUND BARRIER | 60.00 | LF |
60.00
| 0.00 | 60.00 | $120.00 | $7,200.00 |
| 14 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.985
| 0.97 | 0.015 | $15,000.00 | $225.00 |
| 18 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.985
| 0.97 | 0.015 | $6,000.00 | $90.00 |
| 29 | UNCLASSIFIED FILL | 169.00 | CY |
127.00
| 0.00 | 127.00 | $75.00 | $9,525.00 |
| 32 | CONSTRUCT AND REMOVE COFFERDAM | 1.00 | EA |
1.00
| 0.80 | 0.20 | $1,639,519.00 | $327,903.80 |
| 47 | TEMPORARY BOATYARD | 1.00 | LS |
0.90
| 0.70 | 0.20 | $67,580.00 | $13,516.00 |
| 55 | 6-INCH DIAMETER KNIFE GATE VALVE | 1.00 | LS |
1.00
| 0.75 | 0.25 | $8,163.00 | $2,040.75 |
| 63 | ELECTRICAL WORK | 1.00 | LS |
0.78
| 0.65 | 0.13 | $527,783.00 | $68,611.79 |
| 64 | TRAFFIC CONTROL | 1.00 | LS |
0.97
| 0.94 | 0.03 | $196,500.00 | $5,895.00 |
| S-14 | BOATYARD CONTAINER REPLACEMENT | | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |