| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 12.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.10 | 0.10 | $24,000.00 | $2,400.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.10 | 0.10 | $48,000.00 | $4,800.00 |
| 6 | OFFICE FACILITIES | 12.00 | MTH |
3.00
| 2.00 | 1.00 | $5,000.00 | $5,000.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $879,000.00 | $439,500.00 |
| 11 | TRAFFIC CONTROL | 1.00 | LS |
0.20
| 0.10 | 0.10 | $329,000.00 | $32,900.00 |
| 18 | CONCRETE REMOVAL (NON-REINFORCED) | 1,058.00 | CY |
220.00
| 112.00 | 108.00 | $250.00 | $27,000.00 |
| 19 | UNCLASSIFIED EXCAVATION | 8,399.00 | CY |
174.00
| 40.00 | 134.00 | $165.00 | $22,110.00 |
| 20 | CRUSHED MISCELLANEOUS BASE | 6,963.00 | CY |
86.00
| 0.00 | 86.00 | $85.00 | $7,310.00 |
| 21 | TRENCH BACKFILL SLURRY (CLASS 270-E-500) | 98.00 | CY |
20.00
| 14.00 | 6.00 | $234.00 | $1,404.00 |
| 24 | AC PAVEMENT | 2,197.00 | TON |
32.00
| 0.00 | 32.00 | $200.00 | $6,400.00 |
| 25 | AC PAVEMENT(PATCH BACK) | 143.00 | TON |
15.00
| 0.00 | 15.00 | $214.00 | $3,210.00 |
| 34 | PCC CURB & GUTTER, TYPE A2-VAR | 2,101.00 | LF |
1,048.00
| 656.00 | 392.00 | $72.00 | $28,224.00 |
| 35 | PCC WALK & DRIVEWAYS, 4" THICK | 42,626.00 | SF |
8,993.00
| 5,668.00 | 3,325.00 | $14.00 | $46,550.00 |
| 36 | PCC CURB RAMPS | 112.00 | CY |
25.00
| 15.00 | 10.00 | $1,600.00 | $16,000.00 |
| 37 | DETECTABLE WARNING SURFACE | 947.00 | SF |
150.00
| 81.00 | 69.00 | $65.00 | $4,485.00 |
| 38 | CROSS GUTTER | 285.00 | CY |
50.00
| 0.00 | 50.00 | $740.00 | $37,000.00 |
| 47 | 2" CONDUIT (SCH 80 PVC) | 101.00 | LF |
12.00
| 0.00 | 12.00 | $117.00 | $1,404.00 |
| 48 | 3" CONDUIT (SCH 80 PVC) | 960.00 | LF |
320.00
| 0.00 | 320.00 | $140.00 | $44,800.00 |
| 49 | 4" CONDUIT (SCH 80 PVC) | 24.00 | LF |
24.00
| 0.00 | 24.00 | $100.00 | $2,400.00 |
| 126 | TYPE 3 COMPOSITE PULL BOX INCLUDING COVER | 12.00 | EA |
12.00
| 0.00 | 12.00 | $2,400.00 | $28,800.00 |
| 132 | RED BRICK PAVING WITH MORTAR | 9.00 | SF |
9.00
| 0.00 | 9.00 | $84.00 | $756.00 |
|