Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Olympic Boulevard TSSP - Indiana Street to Montebello Boulevard
Contractor: California Professional Engineering, Inc.
19062 San Jose Avenue
La Puente, CA 91748
Project ID: TSM0010287
Federal Number(s): None
Original Contract: $2,514,601.72
Awarded: 6/22/2023
Period Ending: 12/20/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 7.00 6.001.00$500.00$500.00
5IMPLEMENTATION OF BMPS1.00LS 0.72 0.630.09$10,000.00$900.00
6IMPLEMENTATION OF THE LTWHP1.00LS 0.72 0.630.09$5,000.00$450.00
13AC PAVEMENT(PATCH BACK)7.00TON 7.00 0.007.00$2,400.00$16,800.00
15PCC CURB & GUTTER, TYPE A2-VAR198.00LF 198.00 170.0028.00$180.00$5,040.00
16PCC WALK, 4" THICK80.00SF 80.00 0.0080.00$14.40$1,152.00
18DETECTABLE WARNING SURFACE139.00SF 117.00 48.0069.00$210.00$14,490.00
212" CONDUIT (SCH 80 PVC)140.00LF 56.00 44.0012.00$100.00$1,200.00
234" CONDUIT (SCH 80 PVC)270.00LF 134.00 110.0024.00$110.00$2,640.00
253-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)10,710.00LF 3,965.00 1,157.002,808.00$4.25$11,934.00
265-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)1,400.00LF 235.00 35.00200.00$5.50$1,100.00
2712-CONDUCTOR SIGNAL CABLE(EXCLUDING CONDUIT)10,820.00LF 4,260.00 1,324.002,936.00$7.00$20,552.00
28#6 WIRE3,030.00LF 362.00 0.00362.00$2.80$1,013.60
29#10 WIRE18,430.00LF 1,524.00 764.00760.00$2.50$1,900.00
30#12 WIRE1,900.00LF 1,260.00 500.00760.00$2.40$1,824.00
33TYPE III PULL BOX37.00EA 30.00 19.0011.00$1,100.00$12,100.00
38REMOVE TYPE 1 STANDARD (COMPLETE) (EXCL. FOUND.)7.00EA 7.00 5.002.00$800.00$1,600.00
45REMOVE VEHICLE HEAD (COMPLETE)117.00EA 114.00 33.0081.00$150.00$12,150.00
46REMOVE PEDESTRIAN HEAD (COMPLETE)1.00EA 1.00 0.001.00$150.00$150.00
49REMOVE PEDESTRIAN PUSH BUTTON PLATE31.00EA 1.00 0.001.00$10.00$10.00
50REMOVE TYPE 332 CABINET FOUNDATION5.00EA 1.00 0.001.00$2,200.00$2,200.00
62RELOCATE CONTROLLER6.00EA 1.00 0.001.00$750.00$750.00
79TEMPORARY CONTROLLER1.00EA 1.00 0.001.00$5,000.00$5,000.00
89TYPE 332 CABINET FOUNDATION10.00EA 8.00 5.003.00$2,500.00$7,500.00
90PEDESTRIAN PUSH BUTTON POST FOUNDATION3.00EA 2.00 0.002.00$1,500.00$3,000.00
94TYPE 17 STANDARD FOUNDATION2.00EA 2.00 1.001.00$5,000.00$5,000.00
95TYPE 19 STANDARD FOUNDATION5.00EA 4.00 1.003.00$5,000.00$15,000.00
106PEDESTRIAN PUSH BUTTON PLATE96.00EA 11.00 0.0011.00$25.00$275.00
1124-12" LED VEHICLE HEAD (COMPLETE) 6.00EA 4.00 2.002.00$1,746.00$3,492.00
115VIDEO/RADAR DETECTION SYSTEM WITH 17" LCD MONITOR DRAWER (COMPLETE) - OLYMPIC BL @ GERHART AV1.00EA 0.50 0.000.50$52,000.00$26,000.00
118RADAR DETECTION SYSTEM (COMPLETE) - OLYMPIC BL @ GREENWOOD AV1.00EA 0.50 0.000.50$52,000.00$26,000.00
132TRAFFIC CONTROL1.00LS 0.72 0.630.09$88,884.00$7,999.56

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,467,512.61 $1,257,790.45 $209,722.16
Retained $73,375.63 $62,889.53 $10,486.10
Deducted $0.00 $0.00 $0.00
Due $1,394,136.98 $1,194,900.92 $199,236.06



Contact Office Engineer
Contractor Copy  