| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 6.00 | MTH |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 13 | DEWATERING AND BYPASS (WITHIN INLET AND OUTLET WORKS AREA) | 1.00 | LS |
1.00
| 0.60 | 0.40 | $75,000.00 | $30,000.00 |
| 22 | STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 1 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
1.00
| 0.95 | 0.05 | $125,000.00 | $6,250.00 |
| 23 | STEEL LINER REHABILITATION - BUTTERFLY VALVE NO. 2 (ABRASIVELY BLAST, CAVITATION FILLING, COATING) | 1.00 | EA |
1.00
| 0.95 | 0.05 | $150,000.00 | $7,500.00 |
| 28 | TRASH RACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 2 | 1.00 | EA |
1.00
| 0.95 | 0.05 | $150,000.00 | $7,500.00 |
| 32 | HYDRAULIC CYLINDER REFURBISHMENT - BUTTERFLY VALVE NO. 1 (DISASSEMBLY, REFURBISHMENT, RE-ASSEMBLY) | 1.00 | EA |
1.00
| 0.95 | 0.05 | $200,000.00 | $10,000.00 |
| S-14 | COATING 2ND SHIFT - UNIT PRICE $3210/DAY | | DAY |
14.00
| 10.00 | 4.00 | $3,210.00 | $12,840.00 |
| S-19 | TRASHRACK ABRASIVE BLASTING / RECOATING - OUTLET STRUCTURE 1 | | LS |
1.00
| 0.00 | 1.00 | $270,000.00 | $270,000.00 |