Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Bridge Preventive Maintenance Program - Group 16 Cities
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0015922
Federal Number(s): BPMPL-5953(726)
Original Contract: $2,210,300.00
Awarded: 5/20/2024
Period Ending: 1/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)3.00MTH 2.00 1.001.00$500.00$500.00
5IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 1.00 0.500.50$10,000.00$5,000.00
13OFFICE FACILITIES4.00MTH 3.00 2.001.00$15,000.00$15,000.00
16TRAFFIC CONTROL1.00LS 0.75 0.500.25$228,771.00$57,192.75
17FLASHING ARROW SIGN1.00LS 0.75 0.500.25$5,000.00$1,250.00
18CHANGEABLE MESSAGE SIGN1.00LS 0.75 0.500.25$50,000.00$12,500.00
58CLEAN EXPANSION JOINT874.00LF 868.00 584.00284.00$30.00$8,520.00
59JOINT SEAL (MR 1/2")185.00LF 185.00 80.00105.00$120.00$12,600.00
61JOINT SEAL (MR 1-1/2")80.00LF 74.00 0.0074.00$230.00$17,020.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
EXHIBIT 16-Z11 0.00 2.00-2.00$1,000.00 ($2,000.00)
EXHIBIT 9-P1 0.00 2.00-2.00$1,000.00 ($2,000.00)

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,464,783.70 $1,335,200.95 $129,582.75
Retained $73,239.18 $66,760.05 $6,479.13
Deducted $0.00 $4,000.00 ($4,000.00)
Due $1,391,544.52 $1,264,440.90 $127,103.62



Contact Office Engineer