| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
37.00
| 34.00 | 3.00 | $500.00 | $1,500.00 |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
36.00
| 34.00 | 2.00 | $8,000.00 | $16,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
37.00
| 34.00 | 3.00 | $5,000.00 | $15,000.00 |
| 69 | AC CURB, TYPE D2-6 | 22,365.00 | LF |
23,660.00
| 22,365.00 | 1,295.00 | $3.50 | $4,532.50 |
| 70 | AC PAVEMENT | 13,973.00 | TON |
15,214.00
| 13,973.00 | 1,241.00 | $100.00 | $124,100.00 |
| 79 | REINFORCED CONCRETE INTAKE CANAL | 2,190.00 | CY |
2,475.00
| 2,460.00 | 15.00 | $900.00 | $13,500.00 |
| S-32 | REPAIR DAMAGED GATE TRACK | | LS |
1.00
| 0.00 | 1.00 | $19,421.00 | $19,421.00 |
| S-33 | FURNISH & INSTALL (25) DELINEATORS | | LS |
1.00
| 0.00 | 1.00 | $4,200.00 | $4,200.00 |
| S-34 | PRICE ESCALATION FOR RIP RAP AND ASPHALT | | LS |
1.00
| 0.00 | 1.00 | $98,980.00 | $98,980.00 |
| S-35 | SERVICE DROP CONDUCTORS (4) | | LS |
1.00
| 0.00 | 1.00 | $12,497.00 | $12,497.00 |
|