| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
1.00
| 0.98 | 0.02 | $10,000.00 | $200.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.99
| 0.98 | 0.01 | $60,000.00 | $600.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
1.00
| 0.98 | 0.02 | $25,000.00 | $500.00 |
| 14 | OPERATIONAL TESTS | 1.00 | LS |
0.55
| 0.00 | 0.55 | $60,000.00 | $33,000.00 |
| 15 | DEMOLITION | 1.00 | LS |
1.00
| 0.98 | 0.02 | $390,000.00 | $7,800.00 |
| 21 | ELECTRICAL WORK FOR WEST TOLEDO PUMP STATION | 1.00 | LS |
1.00
| 0.97 | 0.03 | $600,000.00 | $18,000.00 |
| 22 | ELECTRICAL WORK FOR WEST NEAPOLITAN PUMP STATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $600,000.00 | $30,000.00 |
| 23 | ELECTRICAL WORK FOR EAST TOLEDO PUMP STATION | 1.00 | LS |
0.98
| 0.95 | 0.03 | $600,000.00 | $18,000.00 |
| 25 | DRILL AND BOND DOWEL (EPOXY CARTRIDGE) | 261.00 | LF |
261.00
| 229.83 | 31.17 | $200.00 | $6,234.00 |
| S-5 | REPLACE ENTRANCE DOOR FRAMES | | LS |
1.00
| 0.98 | 0.02 | $12,500.00 | $250.00 |
| S-10 | GENERAL RENTAL FOR WEST NEAPOLITAN | | LS |
1.00
| 0.00 | 1.00 | $1,650.00 | $1,650.00 |
| S-11 | SUBMERSIBLE PUMP CONDUIT UPSIZE | | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| S-12 | ANNUNCIATOR REPROGRAMMING | | LS |
1.00
| 0.00 | 1.00 | $3,850.00 | $3,850.00 |
| S-13 | PUMP SCHEMATIC CHANGES | | LS |
1.00
| 0.00 | 1.00 | $1,770.00 | $1,770.00 |