Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Slauson Blue Line Station Intersection Improvements
Contractor: Excel Paving Company
2230 Lemon Avenue
Long Beach, CA 90806-5195
Project ID: RDC0016317
Federal Number(s): None
Original Contract: $1,764,264.00
Awarded: 2/28/2023
Period Ending: 11/20/2024
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
30METAL HAND RAILINGS PER STD PLAN 60647.00LF 26.00 0.0026.00$450.00$11,700.00
36INDUCTIVE LOOP DETECTOR AND LEADS SAW CUT1,623.00LF 1,623.00 0.001,623.00$14.00$22,722.00
45PEDESTRIAN PUSH BUTTON1.00EA 1.00 0.001.00$160.00$160.00
46PEDESTRIAN PUSH BUTTON PLATE1.00EA 1.00 0.001.00$30.00$30.00
483-12" LED VEHICLE HEAD (COMPLETE) 1.00EA 1.00 0.001.00$1,600.00$1,600.00
67COUNTDOWN PEDESTRIAN HEAD (COMPLETE)7.00EA 7.00 3.004.00$1,200.00$4,800.00
68250 W LUMINAIRE LED1.00EA 1.00 0.001.00$700.00$700.00
69#3 COMPOSITE PULLBOX4.00EA 4.00 0.004.00$1,800.00$7,200.00
70NO. 6 PULL BOX19.00EA 19.00 12.007.00$1,700.00$11,900.00
712-PAIR DETECTOR LEAD-IN CABLE15.00LF 15.00 0.0015.00$24.00$360.00
S-3PROJECT SUPERVISION AND TRAFFIC CONTROL MAINTENANCE DUE TO SURVEY DELAY LS 1.00 0.001.00$6,936.00$6,936.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 20.00 0.0020.00$2,000.00 $40,000.00
EXHIBIT 16-Z1000 1.00 0.001.00$1,000.00 $1,000.00
EXHIBIT 9-F1000 1.00 0.001.00$1,000.00 $1,000.00
LABOR COMPLIANCE1 2.00 1.001.00$5,000.00 $5,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,619,624.00 $1,551,516.00 $68,108.00
Retained $80,981.20 $77,575.80 $3,405.40
Deducted $52,000.00 $5,000.00 $47,000.00
Due $1,486,642.80 $1,468,940.20 $17,702.60