Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Washington Boulevard TSSP - Atlantic Boulevard to Whittier Boulevard
Contractor: Crosstown Electrical & Data, Inc.
5454 Diaz Street
Irwindale, CA 91706
Project ID: TSM0010285
Federal Number(s): None
Original Contract: $1,990,667.00
Awarded: 2/1/2024
Period Ending: 2/20/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500)1.00LS 0.12 0.000.12$2,500.00$300.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)9.00MTH 1.00 0.001.00$500.00$500.00
3CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000)1.00LS 0.12 0.000.12$1,000.00$120.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.18 0.000.18$5,000.00$900.00
5IMPLEMENTATION OF BMPS1.00LS 0.08 0.000.08$2,500.00$200.00
6MOBILIZATION1.00LS 0.18 0.000.18$85,000.00$15,300.00
192" CONDUIT (SCH 80 PVC)375.00LF 120.00 0.00120.00$104.00$12,480.00
203" CONDUIT (SCH 80 PVC)740.00LF 430.00 0.00430.00$140.00$60,200.00
214" CONDUIT (SCH 80 PVC)100.00LF 100.00 0.00100.00$140.00$14,000.00
29TYPE II PULL BOX5.00EA 3.00 0.003.00$2,200.00$6,600.00
30TYPE III PULL BOX11.00EA 7.00 0.007.00$2,435.00$17,045.00
32NO. 6 PULL BOX INCL PCC COVER22.00EA 13.00 0.0013.00$1,705.00$22,165.00
80TYPE 332 CABINET FOUNDATION3.00EA 2.00 0.002.00$2,295.00$4,590.00
110PEDESTRIAN PUSH BUTTON POST FOUNDATION3.00EA 2.00 0.002.00$1,225.00$2,450.00
142TRAFFIC CONTROL1.00LS 0.20 0.000.20$115,000.00$23,000.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $179,850.00 $0.00 $179,850.00
Retained $8,992.50 $0.00 $8,992.50
Deducted $0.00 $0.00 $0.00
Due $170,857.50 $0.00 $170,857.50



Contact Office Engineer
Contractor Copy  