Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Altadena - Altadena Dr and Washington Blvd Roadway Improvement
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RMD2504001
Federal Number(s): None
Original Contract: $5,543,838.70
Awarded: 1/22/2024
Period Ending: 2/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 9.00 8.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.97 0.950.02$20,000.00$400.00
7IMPLEMENTATION OF THE SWPPP1.00LS 0.97 0.950.02$40,000.00$800.00
12CONCRETE REMOVAL (NON-REINFORCED)297.00CY 367.26 342.0025.26$375.00$9,472.50
13UNCLASSIFIED EXCAVATION352.00CY 487.60 352.00135.60$250.00$33,900.00
15CRUSHED MISCELLANEOUS BASE177.00CY 221.00 177.0044.00$280.00$12,320.00
17TRENCH BACKFILL SLURRY (CLASS 270-E-500)6.00CY 45.00 6.0039.00$400.00$15,600.00
21TEMPORARY AC PAVEMENT (PATCH BACK)15.00TON 83.44 15.0068.44$300.00$20,532.00
24RECONSTRUCT MANHOLE (SEWER)19.00EA 18.00 11.007.00$2,500.00$17,500.00
27PCC PAVEMENT161.00CY 173.50 161.0012.50$480.00$6,000.00
31DRILL AND BOND DOWEL86.00LF 148.00 86.0062.00$80.00$4,960.00
39CURB DRAIN PER STD PLAN 150, N=1, CASE 2 INLET4.00EA 5.00 4.001.00$2,500.00$2,500.00
41PCC CURB, TYPE A1-82.00LF 8.00 2.006.00$300.00$1,800.00
42PCC CURB, TYPE A1-VAR109.00LF 121.00 107.0014.00$80.00$1,120.00
44PCC CURB & GUTTER, TYPE A2-8590.00LF 605.00 603.002.00$95.00$190.00
45PCC CURB & GUTTER, TYPE A2-8, W=VAR38.00LF 44.00 38.006.00$180.00$1,080.00
46PCC CURB & GUTTER, TYPE A2-VAR751.00LF 778.00 751.0027.00$115.00$3,105.00
47PCC WALK & DRIVEWAYS, 4" THICK7,714.00SF 9,785.00 8,228.001,557.00$11.00$17,127.00
49PCC WALK & DRIVEWAYS, 6" THICK746.00SF 1,654.00 1,601.0053.00$24.00$1,272.00
64COMPOSITE TYPE 2 PULL BOX INCL COVER4.00EA 6.00 4.002.00$1,320.00$2,640.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGETED WORKER HIRING PROGRAMSTIP 1,910.69 1,404.81505.88$1.00 $505.88

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,781,010.70 $5,628,192.20 $152,818.50
Retained* $289,050.57 $281,409.64 $7,640.93
Deducted $1,910.69 $1,404.81 $505.88
Due $5,490,049.44 $5,345,377.75 $144,671.69



*This project has an escrow account.

Contact Office Engineer
Nancy Garcia (626) 649-2354
Contractor Copy  
P Please consider the environment before printing this report.