Los Angeles County Public Works
Project Management Division III
Progress Payment 9
Project Name: Naples Island Pump Stations Rehabilitation - Phase I
Contractor: MMC, Inc.
5901 Fresca Drive
La Palma, CA 90623
Project ID: FCC0001392
Federal Number(s): None
Original Contract: $5,854,700.00
Awarded: 6/21/2023
Period Ending: 2/20/2025
Board Accepted: 7/30/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
14OPERATIONAL TESTS1.00LS 0.90 0.800.10$60,000.00$6,000.00
S-14DRAIN PAN PIPE MODIFICATIONS LS 1.00 0.001.00$3,000.00$3,000.00
S-15BUBBLER PANEL COMPRESSOR REPLACEMENT LS 1.00 0.001.00$9,500.00$9,500.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 153.00 122.0031.00$2,000.00 $62,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,972,717.19 $5,954,217.19 $18,500.00
Retained $221,850.86 $265,350.86 ($43,500.00)
Deducted $306,000.00 $244,000.00 $62,000.00
Due $5,444,866.33 $5,444,866.33 $0.00



During the initial processing of this Engineer's Monthly Estimate, the current earnings were found to be less than the combined total of the current retention and current deductions resulting in a "negative payment" condition. In order to resolve the condition, the total retention amount for this project has automatically been decreased by $43,500.00