Los Angeles County Public Works
Project Management Division III
Progress Payment 5
Project Name: Bridge Preventive Maintenance Program - Group 16 Cities
Contractor: Beador Construction Company, Inc.
2900 Bristol Street, Suite D204
Costa Mesa, CA 92626-5981
Project ID: RDC0015922
Federal Number(s): BPMPL-5953(726)
Original Contract: $2,210,300.00
Awarded: 5/20/2024
Period Ending: 3/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
11IMPLEMENTATION OF THE DEBRIS CONTAINMENT AND CONTROL PLAN1.00LS 0.75 0.500.25$30,000.00$7,500.00
16TRAFFIC CONTROL1.00LS 1.00 0.900.10$228,771.00$22,877.10
17FLASHING ARROW SIGN1.00LS 1.00 0.900.10$5,000.00$500.00
18CHANGEABLE MESSAGE SIGN1.00LS 1.00 0.900.10$50,000.00$5,000.00
24MISCELLANEOUS METAL (BRIDGE)2,645.00LB 2,912.00 546.002,366.00$50.00$118,300.00
25CLEAN & PAINT STRUCTURAL STEEL1.00LS 1.00 0.350.65$150,000.00$97,500.00
26CHAIN LINK FENCE, 5' HIGH16.00LF 16.00 0.0016.00$450.00$7,200.00
28DETAIL 9 (THERMOPLASTIC)1,933.00LF 1,933.00 0.001,933.00$2.00$3,866.00
32DETAIL 22 (THERMOPLASTIC)674.00LF 674.00 0.00674.00$3.00$2,022.00
36DETAIL 29 (THERMOPLASTIC)755.00LF 380.00 0.00380.00$3.00$1,140.00
S-3TYPE B JOINT SEAL PIER 3 AT WHITTIER BLVD LS 1.00 0.001.00$7,839.22$7,839.22

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
EXHIBIT 16-Z11 1.00 0.001.00$1,000.00 $1,000.00
EXHIBIT 9-P1 2.00 1.001.00$1,000.00 $1,000.00
LABOR COMPLIANCE1 1.00 0.001.00$27,374.43 $27,374.43

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,097,653.91 $1,823,909.59 $273,744.32
Retained $104,882.69 $91,195.48 $13,687.21
Deducted $30,374.43 $1,000.00 $29,374.43
Due $1,962,396.79 $1,731,714.11 $230,682.68