| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $2,500.00 | $2,500.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 6 | OFFICE FACILITIES | 5.00 | MTH |
0.25
| 0.00 | 0.25 | $7,500.00 | $1,875.00 |
| 7 | MOBILIZATION | 1.00 | LS |
0.50
| 0.00 | 0.50 | $145,000.00 | $72,500.00 |
| 8 | CLEARING AND GRUBBING | 1.00 | LS |
0.50
| 0.00 | 0.50 | $10,000.00 | $5,000.00 |
| 11 | CONCRETE REMOVAL (REINFORCED) | 15.00 | CY |
2.25
| 0.00 | 2.25 | $500.00 | $1,125.00 |
| 13 | TRAFFIC CONTROL | 1.00 | LS |
0.20
| 0.00 | 0.20 | $25,000.00 | $5,000.00 |
| 15 | IRRIGATION SYSTEM | 1.00 | LS |
0.50
| 0.00 | 0.50 | $318,500.00 | $159,250.00 |
| 17 | TREE PROTECTION FENCING | 1.00 | LS |
0.60
| 0.00 | 0.60 | $21,000.00 | $12,600.00 |