Los Angeles County Public Works
Project Management Division III
Progress Payment 10
Project Name: Altadena - Altadena Dr and Washington Blvd Roadway Improvement
Contractor: Sully-Miller Contracting Company
135 South State College Boulevard, Suite 400
Brea, CA 92821
Project ID: RMD2504001
Federal Number(s): None
Original Contract: $5,543,838.70
Awarded: 1/22/2024
Period Ending: 3/6/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)11.00MTH 10.00 9.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 1.00 0.970.03$20,000.00$600.00
7IMPLEMENTATION OF THE SWPPP1.00LS 1.00 0.970.03$40,000.00$1,200.00
50POURED IN PLACE RUBBER WALK, 2" THICK490.00SF 490.00 0.00490.00$35.00$17,150.00
118DETAIL 22 (THERMOPLASTIC)7,562.00LF 8,491.00 4,527.003,964.00$1.65$6,540.60
119DETAIL 29 (THERMOPLASTIC)1,111.00LF 450.00 275.00175.00$3.50$612.50
121DETAIL 38 (THERMOPLASTIC)782.00LF 630.00 440.00190.00$3.75$712.50
125DETAIL 9 (THERMOPLASTIC)12,384.00LF 12,384.00 9,894.002,490.00$1.00$2,490.00
127DETAIL 27B (THERMOPLASTIC)921.00LF 2,457.00 0.002,457.00$2.50$6,142.50
128PAVEMENT MARKINGS (THERMOPLASTIC)4,996.00SF 4,531.00 4,267.00264.00$8.30$2,191.20
1296" STRIPING (THERMOPLASTIC)3,160.00LF 235.00 0.00235.00$1.00$235.00
1308" STRIPING (THERMOPLASTIC)406.00LF 527.00 0.00527.00$3.75$1,976.25
13112" STRIPING (THERMOPLASTIC)394.00LF 254.00 130.00124.00$3.75$465.00
135REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)231.00SF 30.00 0.0030.00$4.50$135.00
137REMOVE 8" STRIPING (THERMOPLASTIC)18.00LF 432.00 0.00432.00$5.00$2,160.00
139TRAFFIC CONTROL1.00LS 1.00 0.840.16$360,000.00$57,600.00
143PLANT ESTABLISHMENT PERIOD1.00LS 1.00 0.001.00$11,000.00$11,000.00
S-23CUSTOM-SIZED CATCH BASIN GRATES LS 1.00 0.001.00$8,402.00$8,402.00
S-28ADDITIONAL STRIPING (ALTADENA DR) LS 1.00 0.001.00$33,529.93$33,529.93
S-29ROOT PRUNE CLEAN UP LS 1.00 0.001.00$7,035.20$7,035.20

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGETED WORKER HIRING PROGRAMSTIP 2,461.61 1,910.69550.92$1.00 $550.92

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,941,688.38 $5,781,010.70 $160,677.68
Retained* $297,084.46 $289,050.57 $8,033.89
Deducted $2,461.61 $1,910.69 $550.92
Due $5,642,142.31 $5,490,049.44 $152,092.87



*This project has an escrow account.

Contact Office Engineer
Nancy Garcia (626) 649-2354
Contractor Copy  
P Please consider the environment before printing this report.