Los Angeles County Public Works
Project Management Division III
Progress Payment 14
Project Name: Willowbrook 2 Project (AHSC)
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: RDC0016424
Federal Number(s): None
Original Contract: $4,219,985.00
Awarded: 6/27/2023
Period Ending: 3/20/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
112REMOVE PAVEMENT MARKINGS (THERMOPLASTIC)1,887.00SF 7,285.00 6,784.00501.00$3.00$1,503.00
117DETAIL 29 (THERMOPLASTIC)493.00LF 530.00 493.0037.00$5.00$185.00
118DETAIL 32 (THERMOPLASTIC)2,653.00LF 2,780.00 2,653.00127.00$6.00$762.00
119DETAIL 38 (THERMOPLASTIC)502.00LF 787.00 762.0025.00$3.00$75.00
1246" STRIPING (THERMOPLASTIC)58.00LF 60.00 58.002.00$4.50$9.00
12612" STRIPING (THERMOPLASTIC)1,101.00LF 1,271.00 1,213.0058.00$5.00$290.00
133SIGN PANEL109.00EA 109.00 80.0029.00$215.00$6,235.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LIQUIDATED DAMAGESDAY 92.00 33.0059.00$2,000.00 $118,000.00

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,228,462.89 $4,219,403.89 $9,059.00
Retained* $69,301.27 $178,242.27 ($108,941.00)
Deducted $184,133.82 $66,133.82 $118,000.00
Due $3,975,027.80 $3,975,027.80 $0.00



During the initial processing of this Engineer's Monthly Estimate, the current earnings were found to be less than the combined total of the current retention and current deductions resulting in a "negative payment" condition. In order to resolve the condition, the total retention amount for this project has automatically been decreased by $108,941.00
*This project has an escrow account.