Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Cogswell Dam Inlet - Outlet Works Rehabilitation Project Phase 2
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001313
Federal Number(s): None
Original Contract: $7,493,500.00
Awarded: 5/7/2024
Period Ending: 4/5/2025
Board Accepted: 8/19/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
7IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 1.00 0.950.05$20,000.00$1,000.00
40FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 11.00EA 0.90 0.000.90$50,000.00$45,000.00
41FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 21.00EA 0.90 0.000.90$50,000.00$45,000.00
42FINAL ACCEPTANCE TESTING - BUTTERFLY VALVE 31.00EA 0.90 0.000.90$50,000.00$45,000.00
S-03BV 1 BODY SEAT ASSEMBLY REPLACEMENT AND INSTALLATION LS 1.00 0.001.00$135,783.00$135,783.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $8,105,382.00 $7,833,599.00 $271,783.00
Retained $405,269.10 $391,679.95 $13,589.15
Deducted $0.00 $0.00 $0.00
Due $7,700,112.90 $7,441,919.05 $258,193.85



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.